Runway road rehabilitation

The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • SaMoTer 2020 Preview: Award for the Simex TFC 400 cutting machine
    February 10, 2020
    Simex picked up the attachments category award for its new TFC 400.
  • Twin layer paving evolves
    November 2, 2012
    Dual layer paving offers benefits to wear life as well as major cost reductions - Mike Woof reports The concept of laying the binder course and wearing course at the same time is not new to the road construction market. Various contractors have been working on systems over a number of years, with several manufacturers helping directly with these projects. A number of firms have investigated this method but three manufacturers in particular, Dynapac and Vögele in Europe and Sumitomo in Japan, have made major
  • Tricky mountain road rebuild job in Phoenix AZ
    June 16, 2021
    North Mountain in Phoenix, Arizona is one of the metropolitan area’s most recognisable landmarks and busiest hiking destinations.
  • Screening efficiency
    May 22, 2012
    Hanson UK’s Ingleton Quarry is improving screening efficiency by employing new ceramic lining technology. The facility has taken advantage of the latest developments from Sandvik to improve performance with the replacement of existing quenched steel liners with ceramic inserts. The quarry, located in the Yorkshire Dales National Park, had wear problems with the steel wear protection plates used in the screening process. This cut efficiency while the plates were also noisy. In order to address the problem th