Concrete paving in Indiana

Important concrete paving work has been carried out in Indiana on key highway connections
April 2, 2021 Read time: 3 mins
Improving the I-74 highway is important to help with transport in Indiana

Indiana is a hub for several major interstate highways that criss cross through the state and has been nicknamed the Crossroads of America. The state is home to more pass-through highways than any state in the US and its roads carry a high percentage of heavy trucks transporting goods.

However, carrying such heavy traffic loads has taken its toll on the existing infrastructure. According to the Indiana state government website, approximately US$30 billion needs to be invested in Indiana’s highways over the next 20 years. Nearly 90% of those dollars are dedicated to improving the condition of existing roads and bridges, boosting safety and drainage issues.

One of the interstates getting much-needed pavement replacement and new bridge superstructures is I-74. The concrete pavement rebuild includes a 13-mile section of I-74 in northern Ripley County, south-east Franklin County and south-west Decatur County. Milestone Contractors is leading the 30-month, $61 million reconstruction project.

To keep drivers safe and reduce roadway congestion on I-74, the project was broken up into three phases focusing on patching, shoulder strengthening, and widening and building crossovers for future traffic shifts.

Milestone Contractors began the 30-month portion of the reconstruction project with significant challenges. Workable hours, traffic and maintenance limited when the firm could be on the road to minimise traffic impact.

Operations focused on concrete pavement construction at the east and west end of the project limits. The traffic on I-74 was shifted to westbound lanes while full-depth pavement replacement was carried out in the eastbound lanes. One lane of traffic, separated by a concrete barrier wall, was maintained in each direction of the westbound side of the highway.

The equipment from Minnich has played an important role in refurbishing
The equipment from Minnich has played an important role in refurbishing

In the last year of construction, the contractor shifted all I-74 traffic to the rebuilt eastbound lanes, with one lane in each direction separated by a concrete barrier wall, while westbound lanes were constructed.

The dowel-pin drilling aspect of the project represented a major challenge. The  limitations of the job challenged the company to have hundreds of holes drilled, prepped and ready before the pour crews came in, which meant they had to be off the road at a certain time.

In order to drill over 900 holes/eight-hour shift, Milestone Contractors used the A-4SCW four-gang self-propelled wireless drill and dust collection system from Minnich Manufacturing.

Terry Burris is general superintendent of concrete operations for Milestone Contractors and commented, “The speed of the drills got us in and out so we could move forward quickly. The safety aspect of the drills with the dust collection system is phenomenal. It makes it a lot easier on your workers when you aren’t fighting the dust.”

“One of the things we like to pride ourselves in is that we are probably one of the few contractors that have the dust collection system on all of our drills,” Friess added.

The contractor also found the service support provided by Minnich helped with its operations on the project. On its completion, the I-74 project was awarded American Concrete Pavement Association’s (ACPA) 2020 “Excellence in Concrete Pavements” silver award for rural divided highways.

For more information on companies in this article

Related Content

  • Moveable barrier cuts costs, aids motorists
    February 20, 2012
    Work on an award-winning US bridge was completed with savings and benefits to motorists through the help of an innovative barrier. The bridge replacement of US 31 over I-465 and Lick Creek in southern Indianapolis, state capital of Indiana, won the 2011 Honor Award from the American Council of Engineering Companies of Indiana. Stephen J. Christian & Associates of Indianapolis completed the design in less than nine months to allow Indiana Department of Transportation (INDOT) to take advantage of the favourab
  • Technology and collaboration bring massive time savings
    December 2, 2021
    The link between any major city and its airport is a crucial one. In Auckland, New Zealand, State Highway 20B connects the city of 1.6 million people with the rest of the nation and the international airport, one of only two roads leading there
  • Terex cranes in a tight spot in Michigan
    February 6, 2017
    Terex cranes have been involved in a multiple bridge repair project in the US More than 96,000 vehicles per day travel a stretch of I-96, including its 52-year-old bridges. The Michigan Department of Transportation is in the midst of a two-year US$77 million project to repair bridges and relieve increasing congestion along Interstate 96 at the U.S. Highway 23 interchange in Livingston County. Toebe Construction along with joint venture partner Kamminga & Roodvoets are bringing in a lot of lifting powe
  • Fast-track Biloxi Bay bridge
    July 18, 2012
    Construction of a bridge destroyed in a hurricane was completed early, and with some added aesthetic benefits Hurricane Katrina, one of the deadliest and costliest natural disasters in US history, made landfall on 29 August, 2005, devastating the Gulf Coast. The US 90 Bridge over Biloxi Bay (connecting the communities of Biloxi and Ocean Springs, Mississippi) was one of many major highway and railroad bridges knocked out of service due to extensive storm damage. The eye of the storm passed 96km west of Bilo