Skip to main content

Concrete paving in Indiana

Important concrete paving work has been carried out in Indiana on key highway connections
April 2, 2021 Read time: 3 mins
Improving the I-74 highway is important to help with transport in Indiana

Indiana is a hub for several major interstate highways that criss cross through the state and has been nicknamed the Crossroads of America. The state is home to more pass-through highways than any state in the US and its roads carry a high percentage of heavy trucks transporting goods.

However, carrying such heavy traffic loads has taken its toll on the existing infrastructure. According to the Indiana state government website, approximately US$30 billion needs to be invested in Indiana’s highways over the next 20 years. Nearly 90% of those dollars are dedicated to improving the condition of existing roads and bridges, boosting safety and drainage issues.

One of the interstates getting much-needed pavement replacement and new bridge superstructures is I-74. The concrete pavement rebuild includes a 13-mile section of I-74 in northern Ripley County, south-east Franklin County and south-west Decatur County. Milestone Contractors is leading the 30-month, $61 million reconstruction project.

To keep drivers safe and reduce roadway congestion on I-74, the project was broken up into three phases focusing on patching, shoulder strengthening, and widening and building crossovers for future traffic shifts.

Milestone Contractors began the 30-month portion of the reconstruction project with significant challenges. Workable hours, traffic and maintenance limited when the firm could be on the road to minimise traffic impact.

Operations focused on concrete pavement construction at the east and west end of the project limits. The traffic on I-74 was shifted to westbound lanes while full-depth pavement replacement was carried out in the eastbound lanes. One lane of traffic, separated by a concrete barrier wall, was maintained in each direction of the westbound side of the highway.

The equipment from Minnich has played an important role in refurbishing
The equipment from Minnich has played an important role in refurbishing

In the last year of construction, the contractor shifted all I-74 traffic to the rebuilt eastbound lanes, with one lane in each direction separated by a concrete barrier wall, while westbound lanes were constructed.

The dowel-pin drilling aspect of the project represented a major challenge. The  limitations of the job challenged the company to have hundreds of holes drilled, prepped and ready before the pour crews came in, which meant they had to be off the road at a certain time.

In order to drill over 900 holes/eight-hour shift, Milestone Contractors used the A-4SCW four-gang self-propelled wireless drill and dust collection system from Minnich Manufacturing.

Terry Burris is general superintendent of concrete operations for Milestone Contractors and commented, “The speed of the drills got us in and out so we could move forward quickly. The safety aspect of the drills with the dust collection system is phenomenal. It makes it a lot easier on your workers when you aren’t fighting the dust.”

“One of the things we like to pride ourselves in is that we are probably one of the few contractors that have the dust collection system on all of our drills,” Friess added.

The contractor also found the service support provided by Minnich helped with its operations on the project. On its completion, the I-74 project was awarded American Concrete Pavement Association’s (ACPA) 2020 “Excellence in Concrete Pavements” silver award for rural divided highways.

For more information on companies in this article

Related Content

  • Texas highway project awarded
    May 31, 2019
    A joint venture team has been awarded the US$1.7 billion I-635 LBJ East infrastructure project in Dallas, Texas. Fluor Corporation heads the joint venture, which also includes Balfour Beatty Infrastructure. The partners will carry out the contract to design and construct the I-635 LBJ East Project in Dallas for the Texas Department of Transportation (TxDOT). The scope of work includes the widening and full reconstruction of nearly 18km of the I-635 route, which is also known as LBJ Freeway. In addition, th
  • Dynapac’s digital solutions deliver data driven compaction for Swedish tunnel project
    May 1, 2022
    The project of a double-track 8 km long extension of the railroad line between Varberg and Hamra includes a new 3.1 km long tunnel. This new double track on the West Coast Railway is scheduled to be opened to traffic in 2024. Leading Swiss construction and infrastructure specialist Implenia is using state-of-the-art technology and data acquisition solutions on a fleet of Dynapac CA5000D Seismic rollers for the work under the town of Varberg. The focus is on efficiency, environmental improvement and road safety.
  • Doka’s Voest Bridge bypass project
    February 10, 2020
    The Voest Bridge over the Danube River is part of the A7 Mühlkreis Autobahn through Linz, Austria, is 40 years. Two bypass bridges are being constructed alongside the existing cable-stayed bridge as part of the client ASFINAG’s strategy to boost traffic capacity - around 100,000 vehicles cross the old bridge each day.
  • Ambitious road tunnelling projects around the world
    November 29, 2013
    The construction of the world’s longest subsea road tunnel in Norway and a vital new link under the Bosphorus Strait in Turkey are among a host of exciting, major road tunnel-based projects currently being undertaken across the globe. Guy Woodford reports Sandvik DTi series tunnelling jumbos are being used for the excavation of Solbakktunnel, set to become the world’s longest subsea road tunnel.