Recycled asphalt cuts costs, maximises performance

The need to maximise road performance and cut costs has resulted in Indonesian contractors being keen to adopt cold recycling methods
February 10, 2012 Read time: 4 mins
Using the cold recycling techniques in Indonesia will deliver longer lasting road surfaces at a low cost

Over the last 10 years, pavement recycling has become a popular method for road repairs on major roads in Indonesia. The methods used include pavement rehabilitation using foamed cold mix asphalt technology, which has become particularly popular in recent years. Using pavement recycling offers a good return on investment and energy savings. The fact that this also offers environmental benefits is a plus factor.

As a result of the potential benefits, contractors are interested in recycled asphalt pavement (RAP) materials from damaged pavements. Currently, cold recycling techniques are widely used and present major advantages.

There is a substantial need for road repairs in Indonesia, with vehicle overloading and intermixing of pavements material amongst the problems that contribute to pavement deterioration. According to the country's Institute of National Road Development-IV, the issue of truck overloading is a major problem and has resulted in the 2540 Indonesian Road Authorities (Bina Marga) requiring much stronger pavements.

Before introducing foam cold mix asphalt as a pavement rehabilitation method, several full-scale trials were performed by the Indonesian Road Research and Development Center (Pusjatan).

One pavement recycling trial used Portland cement as a binder in the sub-base layer and this was carried out on a section of the North Coastal Java road, between Jatibarang and Palimanan. This project used cement treated recycled sub-base (CTRB). Pavement recycling using foam cold mix asphalt and cement as an active filler in the base layer was also used on the same stretch of the North Coastal Java road. This trial used cold mix recycling base by foam bitumen (CMRFB).

In 2008, the Indonesian Government introduced a series of pavement recycling projects through its ministry of public works. One of the project sections is the 11km stretch of dual carriageway running from Palimanan- Jatibarang- Cirebon.

PT Stabilised Pavements Indo and one of state-owned enterprises, PT Adhi Karya, as awarded the US$11.5 million design and build project. As a leading stabilisation and road recycling contractor, PT Stabilized Pavements Indo (SPI) performed re-engineering (field investigation and laboratory testing) to find the optimal mix design.

In-situ stabilising equipment, including a Wirtgen recycler, a CMI RS-500 recycler and a Wirtgen W2000 milling machine, was transported to Cirebon to carry out the project. Other machines used included a Hamm smooth drum roller and a Hamm padfoot roller as well as a grader and a binder spreader.

An average of 300mm thick of old asphalt pavement was milled using the planer and placed beside the lane being rebuilt. The material grade of this milled asphalt was comparatively coarse and was not suitable for much of the foamed bitumen work. The surface of the lower layer of the road could then be covered with cement using a purpose-built spreader that can accurately place the binder within 10% of the design spread rate.

The binder was then mixed into the host material using a stabiliser. Mixing was carried out at least two times to ensure that the binder mix would be homogenous. At first mixing was carried out without water and during further mixing, water was added to provide the optimum moisture content for compaction, which was carried out immediately afterwards. The surface was then graded to the required finish and the bottom layer pavement (CTRB) technique was then used.

Foam cold mix asphalt provides an efficient method of delivering pavement flexibility, with the advantage of boosting durability and waterproofing. Because the surface is flexible the risk of cracking over time is reduced and the system also allows a contractor to use thinner wear courses, which cuts costs. Other advantages include increased load bearing capacity, a quick construction method and the ability to re-open a road immediately after work has been completed. In Indonesia the pavement construction layers after rehabilitation consist of a 300mm layer of CTRB, a 250mm layer of CMRFB and a 110mm layer of top courses using new hotmix. Calculations by Indonesian Road Authorities suggest that this type of pavement structure is able to offer a design of 134 million single axle loads.

Related Content

  • Asphalt plant innovations from key firms
    June 12, 2017
    Asphalt plant builders continue to develop new technologies to meet different demands from clients. Marini says that in addition to developing new and more sophisticated asphalt plants, the firm is also meeting demands from customers looking to upgrade existing asphalt plants with the addition of new systems. These can be used to boost output and material quality, while also delivering new grades of mixes. At the same time, plant upgrades can reduce the environmental profile of a plant, while improving its
  • Innovative advances in warm Mix Asphalts
    February 1, 2013
    Rising energy costs and increased awareness of safety and environmental issues have encouraged the development of Warm Mix Asphalts (WMA), which are typically produced at temperatures of between 130°C and 145°C, compared with around 175°C for traditional Hot Mix Asphalt (HMA). WMAs are regularly used in many European countries, as well as both North and South America. The three most common ways to lower the working temperature of asphalt are: a) foaming technologies; b) wax additives; and c) chemical (surfa
  • Nynas and Shell in Hanson UK bio-binder trial
    March 6, 2023
    Hanson UK is using Nynas’s biogenic binder Nypol RE in one asphalt mixture and Shell’s new bio-component binder Cariphalte CarbonSink in the second mix.
  • In the fast lane at Indian F1 track
    June 21, 2012
    India’s new Formula 1 motor racing circuit, with its tight construction tolerances, demands considerable driving skill. More than 500 million people worldwide watched the first Formula 1 motor race in India's history. The drivers were thrilled by the new asphalt circuit with its numerous bends and the peripheral area around the new race track at Greater Noida near the capital New Delhi, which were built by machinery from German company Vögele (a member of the Wirtgen Group). Working with four Super 1800-