Rainforest road construction challenge in Malaysia

Working in a rainforest area can be challenging, but in a rural area outside of Kuching in East Malaysia, a road construction crew was able to carry out a project successfully One of the biggest challenges came from the moisture levels as the area has an average annual rainfall of 4200mm. The saturated soil complicates the construction process on many levels, including stabilisation and compaction. However this heavy moisture content in the soil is a constant for Geocrete Specialist crews, which handl
October 3, 2014 Read time: 2 mins
Despite challenging conditions, contractor Geocrete Specialist has been successful building new road links
Working in a rainforest area can be challenging, but in a rural area outside of Kuching in East Malaysia, a road construction crew was able to carry out a project successfully

One of the biggest challenges came from the moisture levels as the area has an average annual rainfall of 4200mm. The saturated soil complicates the construction process on many levels, including stabilisation and compaction.

However this heavy moisture content in the soil is a constant for Geocrete Specialist crews, which handles road building work in the area. There is seldom time for the soil to dry, as there are 247 rainy days per year. In addition, Kuching receives only five hours of sunshine each day, making the soil heavy for the crews.
Geocrete Specialist handles all aspects of road building, but specialises in stabilisation. That specialisation led the company to recently purchase a reclaimer, with plans to put it to work on a rural road outside Kuching, the capital city in the state of Sarawak in East Malaysia. Geocrete Specialist also has projects to complete in the city. That means its 178 Caterpillar RM500 Road Reclaimer has to be sufficiently versatile to overcome moist soil conditions during stabilisation, while also being able to adjust to projects requiring reclamation of asphalt roads.

The company recently took on a 1.7km job, which required the reclamation of about 1000tonnes of material. The existing asphalt surface varied between 50-75mm. The RM500 was required to make a pass at a depth of 280mm. The machine proved productive and easy to operate and the reclaimed material was graded and compacted. Between three and five vibratory passes were typically required for the soil to reach its target density. The compactor worked close to the reclaimer, with only 5m separating the machines at times. Asphalt was then placed on top of the compacted and graded soil.

The Cat dealer was able to help with service needs, having first advised Geocrete Specialist on selecting a properly-sized machine for its needs. Later, trainers from Caterpillar and the Cat dealer also provided classroom lessons and even helped on the jobsite when the machine was first put to work.

For more information on companies in this article

Related Content

  • Brazilian contractor uses novel methods for high quality road
    January 5, 2015
    Cold-in place recycling method provides fast road rebuild in Brazil In Brazil a road contractor has carried out a high quality road rebuilding job, using novel techniques. Contractor Brown Brown is located in Santa Teresinha in the state of Bahia and recently carried out a two-week job for the company to rehabilitate sections of highway BR-381. The highway is an important route in Brazil and runs from Sao Paulo to Belo Horizonte. Highway BR-381 or Rodovia Fernão Dias, as it is called, stretches some 576km
  • Airport's high demands on asphalt and concrete techniques
    July 11, 2012
    Airport runway, taxiway and parking areas make high demands on paving requirements, both with concrete and asphalt techniques. Mike Woof reports. High quality surface finishes are required in airport environments for runways, taxiways and aircraft parking areas. Because of the speed at which aircraft take off and land and the massive forces exerted due to the weight of the aircraft, particularly during landing, runway structures need to be incredibly strong. The surfaces also have to be constructed to very
  • Compaction in the field
    July 31, 2012
    Special applications require stringent quality control and with compaction machines a key part of the paving process, their contribution can be vital. A high quality finish has helped athletes breaking sporting records on the track at the Shanghai Stadium in China during this year's 2008 Summer Olympic Games. Built in 1997 the stadium has been the venue for numerous major sporting events prior to the Olympics, however its track was showing signs of wear and the local authorities decided that a full refurbis
  • New radio wave technology assesses asphalt integrity
    March 14, 2017
    Real time information on asphalt density and uniformity can boost construction quality - *Roger Roberts, GSSI. Properly compacted asphalt is a major factor in the lifespan of a road, as inadequately compacted asphalt deteriorates at a more rapid rate than properly compacted material. With the billions spent on road construction and repairs each year, it has become a matter of urgency to find new technologies that can ensure the integrity of asphalt on newly paved roads. New radio wave technology is now avai