Rainforest road construction challenge in Malaysia

Working in a rainforest area can be challenging, but in a rural area outside of Kuching in East Malaysia, a road construction crew was able to carry out a project successfully One of the biggest challenges came from the moisture levels as the area has an average annual rainfall of 4200mm. The saturated soil complicates the construction process on many levels, including stabilisation and compaction. However this heavy moisture content in the soil is a constant for Geocrete Specialist crews, which handl
October 3, 2014 Read time: 2 mins
Despite challenging conditions, contractor Geocrete Specialist has been successful building new road links
Working in a rainforest area can be challenging, but in a rural area outside of Kuching in East Malaysia, a road construction crew was able to carry out a project successfully

One of the biggest challenges came from the moisture levels as the area has an average annual rainfall of 4200mm. The saturated soil complicates the construction process on many levels, including stabilisation and compaction.

However this heavy moisture content in the soil is a constant for Geocrete Specialist crews, which handles road building work in the area. There is seldom time for the soil to dry, as there are 247 rainy days per year. In addition, Kuching receives only five hours of sunshine each day, making the soil heavy for the crews.
Geocrete Specialist handles all aspects of road building, but specialises in stabilisation. That specialisation led the company to recently purchase a reclaimer, with plans to put it to work on a rural road outside Kuching, the capital city in the state of Sarawak in East Malaysia. Geocrete Specialist also has projects to complete in the city. That means its 178 Caterpillar RM500 Road Reclaimer has to be sufficiently versatile to overcome moist soil conditions during stabilisation, while also being able to adjust to projects requiring reclamation of asphalt roads.

The company recently took on a 1.7km job, which required the reclamation of about 1000tonnes of material. The existing asphalt surface varied between 50-75mm. The RM500 was required to make a pass at a depth of 280mm. The machine proved productive and easy to operate and the reclaimed material was graded and compacted. Between three and five vibratory passes were typically required for the soil to reach its target density. The compactor worked close to the reclaimer, with only 5m separating the machines at times. Asphalt was then placed on top of the compacted and graded soil.

The Cat dealer was able to help with service needs, having first advised Geocrete Specialist on selecting a properly-sized machine for its needs. Later, trainers from Caterpillar and the Cat dealer also provided classroom lessons and even helped on the jobsite when the machine was first put to work.

For more information on companies in this article

Related Content

  • Caterpillar’s connective technology boosts customer productivity
    January 6, 2017
    Caterpillar and its German dealer Zeppelin Baumaschinen, are exhibiting the manufacturer’s latest technologies for machine efficiency under the theme “Built for It”. The focus is Cat Connect Technology, which is base hardware or software technology available for Cat or competitive equipment. The technology can be factory fitted or dealer installed. Operators can see machine performance and movements via on-board touchscreens. Site managers can view machine performance and site movements to guide the assets
  • What matters most: an expert’s insight into purchasing light equipment
    July 19, 2021
    Sometimes, it seems that the biggest differentiator between various brands of light equipment is their paint colour. Yet there is plenty to compare when you look beyond the surface.
  • Runway resurfacing in Sardinia with Wirtgen machines
    December 7, 2017
    The fleet used comprised two Wirtgen W 210s and one W 200i, as well as two Wirtgen WR 2000 soil stabilisers. Located roughly 8 km north-west of the city of Alghero, Alghero-Fertilia Airport is one of three commercial airports on the Italian island, along with Cagliari Elmas and Olbia. Built as a military airport in the late 1930s, Alghero-Fertilia still occasionally handles military aircraft. However commercial flights represent its main traffic and as it serves the provinces of Sassari and Oristano, it is
  • Road milling advances from key players
    January 30, 2020
    Major manufacturers have introduced key innovations in milling, recycling and stabilisation