Rainforest road construction challenge in Malaysia

Working in a rainforest area can be challenging, but in a rural area outside of Kuching in East Malaysia, a road construction crew was able to carry out a project successfully One of the biggest challenges came from the moisture levels as the area has an average annual rainfall of 4200mm. The saturated soil complicates the construction process on many levels, including stabilisation and compaction. However this heavy moisture content in the soil is a constant for Geocrete Specialist crews, which handl
October 3, 2014 Read time: 2 mins
Despite challenging conditions, contractor Geocrete Specialist has been successful building new road links
Working in a rainforest area can be challenging, but in a rural area outside of Kuching in East Malaysia, a road construction crew was able to carry out a project successfully

One of the biggest challenges came from the moisture levels as the area has an average annual rainfall of 4200mm. The saturated soil complicates the construction process on many levels, including stabilisation and compaction.

However this heavy moisture content in the soil is a constant for Geocrete Specialist crews, which handles road building work in the area. There is seldom time for the soil to dry, as there are 247 rainy days per year. In addition, Kuching receives only five hours of sunshine each day, making the soil heavy for the crews.
Geocrete Specialist handles all aspects of road building, but specialises in stabilisation. That specialisation led the company to recently purchase a reclaimer, with plans to put it to work on a rural road outside Kuching, the capital city in the state of Sarawak in East Malaysia. Geocrete Specialist also has projects to complete in the city. That means its 178 Caterpillar RM500 Road Reclaimer has to be sufficiently versatile to overcome moist soil conditions during stabilisation, while also being able to adjust to projects requiring reclamation of asphalt roads.

The company recently took on a 1.7km job, which required the reclamation of about 1000tonnes of material. The existing asphalt surface varied between 50-75mm. The RM500 was required to make a pass at a depth of 280mm. The machine proved productive and easy to operate and the reclaimed material was graded and compacted. Between three and five vibratory passes were typically required for the soil to reach its target density. The compactor worked close to the reclaimer, with only 5m separating the machines at times. Asphalt was then placed on top of the compacted and graded soil.

The Cat dealer was able to help with service needs, having first advised Geocrete Specialist on selecting a properly-sized machine for its needs. Later, trainers from Caterpillar and the Cat dealer also provided classroom lessons and even helped on the jobsite when the machine was first put to work.

For more information on companies in this article

Related Content

  • Reclaimer/stabilisers are helping rebuild roads in South Africa
    October 3, 2014
    Contractor Nyoni Projects is taking a new approach to two major road upgrades in the North West Province of South Africa. The company is refining its fleet and processes with the use of two new Caterpillarr RM300 reclaimer/recyclers. By introducing these new machines and the associated working methods, the firm believes it can help meet the country’s growing road repair, reclamation and building needs. The firm has seen an increase in productivity since it started using the machines. Maclaud Nyoni, m
  • Success of hot mix asphalt road recycling
    March 7, 2012
    Russian construction firm Kamdorstroy has carried out a successful demonstration of recycling techniques to over 60 highway officials, academics and contractors from all over the CIS states. The demonstration was carried out in co-operation with the Russian Federal Highway and Tatarstan Highway authorities and involved milling, recycling and overlaying a road with hot mix asphalt. The work was carried out on a 7.5m wide roadway with 3.8m wide lanes (with an overlap) using machinery and techniques new to Rus
  • Historic Oakland Bay Bridge receives a new asphalt road surface
    March 31, 2014
    Part of an iconic US bridge has been given a new lease of life, as Mike Woof reports The western section of the historic Oakland Bay Bridge in the US state of California has recently benefited from a series of improvements to strengthen its structural integrity and also upgrade the running surface. Contractor OC Jones & Sons of Berkeley CA, paved large portions of the bridge, taking on two different projects as part of the work. First was placement of the specialised epoxy on the self-anchored suspension (S
  • Caterpillar meets the challenges
    February 14, 2012
    Roads in south-eastern France and those on the west coast of Spain share a common challenge often faced by road construction crews around Europe: extremely tight working conditions. According to Caterpillar, such conditions create construction demands that can affect traffic flow, the preservation of historic structures and even the ability to resurface these narrow roads that, in some cases, have been around for centuries. Add to these challenging working conditions, the mountainous terrain found in the Al