Skip to main content

Cost-effective cold mix asphalt recycling

In Lithuania, cold mix asphalt containing recycled asphalt pavement has been installed in a new base course overlay for a section of the A1, the country's most heavily trafficked motorway.
February 17, 2012 Read time: 3 mins
Zemaitijos Keliai's cold mix plant, which was set up a short distance from the site

In Lithuania, cold mix asphalt containing recycled asphalt pavement has been installed in a new base course overlay for a section of the A1, the country's most heavily trafficked motorway.

The all-important bitumen emulsion binder, Nymuls RX, was produced locally under licence from bitumen specialist 294 Nynas.

The A1 is Lithuania's main cross-country route, linking the capital Vilnius in the east, westwards to Kaunas and then Klaipeda by the Baltic Sea. Maximum traffic density along the 300km long, dual four-lane highway is 40,000 vehicles/day.

It is towards Klaipeda that a 3.4km stretch of the motorway's eastbound carriageway was giving particular trouble. Built in the mid-1980s this portion of road had an experimental 200mm thick base course of fly ash stabilised gravel, mixed to meet the then prevailing Soviet standards. But 25 years on, the bitumen bound layers above the base course displayed extensive reflected cracking.

"Over time, the base course has developed considerable strength, becoming a semi-rigid pavement rather than the flexible one it was supposed to be," says deputy director of the Lithuanian Road Administration (LRA) Petras Tekorius.

Weather-induced movement caused the rigid material to crack, with a detrimental effect on the asphalt above.

"We had two problems in reinstating the carriageway: what to do with the base course, and how to rebuild the pavement in the best way." The original base course had considerable residual bearing capacity, despite the cracks. "So we decided to leave the original base course in situ, but to cap it first with a 120mm thick unbound layer of crushed stone to form an anti-cracking and levelling medium, and then a new 200mm base course of cold recycled asphalt," says Tekorius.

This would introduce to the carriageway sufficient elasticity, according to LRA's head of Roads Division Zigmantas Perveneckas. As to the choice of recycled cold mix asphalt, this seemed the natural thing to do.

"We are doing our utmost to implement sustainable technologies in the roads industry," he says.

The LRA has used cold mix recycling on a number of road projects since the early 2000s, prompted by European bitumen specialist Nynas. Although the roads involved were of a lesser nature than the A1, their successful refurbishment has bred sufficient confidence for a more substantial challenge to be undertaken. Certainly, the A1 is the big one, in terms of cold recycling.

Roads civil engineering contractor responsible for the A1 recycling is 2826 Zemaitijos Keliai, which has invested substantially in the technology. It owns trailer-mounted cold mix plant designed by Aneco of Sweden, and it has a licence from Nynas to produce Nymuls RX, a premier bitumen emulsion binder used in cold mix.

"Our investment is paying off: we have had to build the market for cold mix recycled asphalt but now the contracts are coming through," says the company's deputy director Alvydas Peldzius, who pays tribute to the assistance given by Nynas in providing technological guidance and training.

The A1 section under repair first had its three existing asphalt layers milled off and the planings graded and stockpiled at a temporary mixing plant set up 2km from the site. Crushed stone was placed on the original base course, to form the stress absorbing layer. Then production of the cold mix for the new base course began, using the reclaimed asphalt; an amount of virgin aggregate to make up the required volume; fillers and the Nymuls RX bitumen emulsion, to create the base course.

After this material had been placed, in two layers each of 100mm, amounting to 30,000tonnes, an 80mm thick hot asphalt concrete binder course was added, followed by a 40mm stone mastic asphalt surface course.

The direct cost saving of the recycled solution over conventional construction was around 20%, much more when sustainability and environmental benefits are added.

For more information on companies in this article

Related Content

  • Arizona Chemical study reveals lower CO2 footprint with RAP additive
    May 18, 2015
    A life-cycle assessment has found that an asphalt mix containing a high percentage of reclaimed asphalt pavement (RAP) along with an additive by Arizona Chemical can produce a significantly lower carbon footprint than virgin asphalt mix or a mix containing a low percentage of RAP. The assessment study was carried out by third party Arthur D. Little, an international management consulting firm, using Arizona Chemical’s SYLVAROAD RP 1000 performance additive. The work noted that cradle-to-gate, a road aspha
  • COLAS is offering innovative infrastructure solutions
    November 15, 2013
    As a leader in the construction and maintenance of transport infrastructure, COLAS has long prioritised research and development. The company is a leader in the field of new solutions for road surfacing systems. Its research and development teams now offer a vast global technical network of 2000 research specialists, engineers and technicians. These teams continue to focus on areas such as environmental protection issues, and in particular saving energy and materials and reducing carbon impact. They also f
  • Asphalt paver proven in tough applications
    February 16, 2012
    BOMAG says that its new BF800 paver has now been well proven in tough working applications.
  • Asphalt paver proven in tough applications
    April 10, 2012
    BOMAG says that its new BF800 paver has now been well proven in tough working applications. The newly developed BF800 follows the same basic design principles of the smaller BF300 and BF600 models and weighs in at 20tonnes, with a maximum screed width of 2.5-10m. Extensive testing of the BF800 was carried out in an array of difficult operations and in late 2010 some 14,000tonnes of asphalt was laid in 3.5 days in 24-hour shifts to reconstruct the Brenner highway on the A22 near Bozen in northern Italy.