Asphalt milling key to runway upgrade project

Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city. The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point. As part of the overall master plan for the modernisation of CSIA, Mumbai International Airport (MIAL) is completely reconstructing both the runways to create an efficient airside infrastructure, which is the core of an
April 5, 2012 Read time: 2 mins

Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city.

The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point.

As part of the overall master plan for the modernisation of CSIA, Mumbai International Airport (MIAL) is completely reconstructing both the runways to create an efficient airside infrastructure, which is the core of an airport. It will bring the runways up to international standards in order to handle the larger Airbus A380s.

The primary runway work is scheduled for completion about now while the intersection between the two runways is closed for reconstruction for four hours, one day a week until March.

As part of the scheme 1144 Gmmco, India's largest 178 Caterpillar dealer, sealed a deal to sell the first new 2m PM200 cold planer in India to contractor 1145 Ashwini Infra Developments, which was hired to carry out the milling and asphalting of the secondary runway reconstruction project at the CSIA.

The crews are only able to complete the project during overnight hours and that "required tight planning and firm schedules. Any breakdown would result in the complete abandonment of plans." Ashwini Infra Developments already owned a Cat PM102, and its previous experience "made the decision to purchase the new PM200 easy." Ravi Goudar, director, AID, said: "Gmmco has been very supportive as a dealer and we are very happy with their service. Hence, when it came to choosing a bigger milling machine we went with a Caterpillar PM200."

For more information on companies in this article

Related Content

  • New asphalt compaction technologies boost quality
    April 13, 2012
    More sophisticated compaction technologies are now coming to market, offering a wide range of benefits to users While asphalt paving techniques vary widely between North America and Europe, there is greater commonality in the compaction methods required. New developments in compaction rollers are offering contractors using both North American and European style paving techniques major gains in quality. According to Robert Horan, a regional engineer for the US-based Asphalt Institute, intelligent compact
  • G&Z paving Canada’s longest runway
    October 12, 2012
    A contractor in Canada, Dufferin Construction, is using three items of new equipment bought from Guntert & Zimmerman to pave the country’s longest runway. The project is extensive, featuring a new runway measuring 4.3km long by 60m wide, an apron area measuring 145,000m2 and two taxiways, each 3.8km long by 25m wide. In all, the work requires 1.5 million tonnes of base aggregate, and 200,000m2 of cement-stabilised base. Dufferin Construction Company, a division of Holcim (Canada) already owns two other G&Z
  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this
  • Benningoven builds special plant for Norwegian firm
    August 18, 2015
    Benninghoven has built an asphalt plant specially to order for a customer in Norway. Contractor Veidekke had a tight timeframe in which the plant could be erected at the firm’s chosen site in Sörli, as well as specific requirements as to its configuration. Benninghoven was able to construct the special TBA 4000 UC asphalt mixing plant to the firm’s request. A notable feature of the plant is that its large capacity materials towers stand 33m high. The order was received in January 2014, with the plant the