Asphalt milling key to runway upgrade project

Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city. The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point. As part of the overall master plan for the modernisation of CSIA, Mumbai International Airport (MIAL) is completely reconstructing both the runways to create an efficient airside infrastructure, which is the core of an
April 5, 2012 Read time: 2 mins

Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city.

The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point.

As part of the overall master plan for the modernisation of CSIA, Mumbai International Airport (MIAL) is completely reconstructing both the runways to create an efficient airside infrastructure, which is the core of an airport. It will bring the runways up to international standards in order to handle the larger Airbus A380s.

The primary runway work is scheduled for completion about now while the intersection between the two runways is closed for reconstruction for four hours, one day a week until March.

As part of the scheme 1144 Gmmco, India's largest 178 Caterpillar dealer, sealed a deal to sell the first new 2m PM200 cold planer in India to contractor 1145 Ashwini Infra Developments, which was hired to carry out the milling and asphalting of the secondary runway reconstruction project at the CSIA.

The crews are only able to complete the project during overnight hours and that "required tight planning and firm schedules. Any breakdown would result in the complete abandonment of plans." Ashwini Infra Developments already owned a Cat PM102, and its previous experience "made the decision to purchase the new PM200 easy." Ravi Goudar, director, AID, said: "Gmmco has been very supportive as a dealer and we are very happy with their service. Hence, when it came to choosing a bigger milling machine we went with a Caterpillar PM200."

For more information on companies in this article

Related Content

  • Airport upgrade
    July 2, 2012
    Four Dynapac CA602D single drum soil compactors are helping redevelopment work at Muscat International Airport in Oman. The machines are compacting around 160,000m2 of rockfill as part of a project to increase the airport's passenger handling capacity from 5-12 million/year by 2011. To minimise runway or taxiway flooding risks, the grounds are being raised 3m by local contractor Galfar Engineering & Contracting SAOG and this requires 10-12 million m3 of desert sand and crushed rock. The 19tonne Dynapac roll
  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • Meeting the challenge of desert runway resurfacing
    February 8, 2012
    Ferocious daytime temperatures can provide a tough challenge to construction firms working in desert conditions in Egypt's south. Despite the high daytime temperatures however, Egyptian contractor Orascom has managed to complete an airport project on budget and ahead of schedule, while meeting the client's tight specifications.
  • Beijing airport runway features novel asphalt solution
    December 7, 2017
    Beijing ranks amongst the five busiest airports across the globe and its runway surfaces face tough stresses as a result. Over 94 million passengers flew through Beijing Capital Airport (BCA) in 2016 and as many as 70 flights/hour can take off and land during peak times. The 60m-wide middle runway of Beijing Capital International Airport is the busiest of the three runways, with a landing and take-off flight ratio of up to 40%. This runway was first rehabilitated in 1996 and then repaired in 2013 and 2015