Fast bridge building in Tennessee

The Tennessee Department of Transportation (TDOT) recently completed the Fast Fix 8 bridge project in Nashville, with help from a Power Curbers slipformer belonging to Irwin Concrete Construction. TDOT’s goal was to replace eight ageing interstate bridges along Interstate 40 through Nashville using a process called Accelerated Bridge Construction (ABC). This uses fast-paced, around-the-clock work to limit road closures and speed up bridge completion, impacting surrounding communities as little as possibl
July 5, 2016 Read time: 3 mins
A novel method of high speed construction was used during weekend possessions to minimise disturbance to commuters and residents
The Tennessee Department of Transportation (TDOT) recently completed the Fast Fix 8 bridge project in Nashville, with help from a 307 Power Curbers slipformer belonging to Irwin Concrete Construction.

TDOT’s goal was to replace eight ageing interstate bridges along Interstate 40 through Nashville using a process called Accelerated Bridge Construction (ABC). This uses fast-paced, around-the-clock work to limit road closures and speed up bridge completion, impacting surrounding communities as little as possible.

The 2410 Federal Highway Administration, a division of the US DOT, estimates that approximately 25% of bridges in the US are in need of rehabilitation, repair, or replacement and are “structurally deficient.” The bridges over Charlotte Avenue, Jo Johnston Avenue, Clinton Street, and Herman Street in downtown Nashville were built in 1968. Their condition began to deteriorate and in 2013, chunks of concrete began falling from the Charlotte Avenue overpass, causing road closures and concerns about the safety of the downtown bridges.

The Fast Fix project was scheduled for 13 weekends, where both directions of I-40 were closed from the I-40/I-65 split west of downtown to the split south of downtown every weekend to allow crews complete access to replace each bridge.

The interstate would close on Friday night after rush hour, when crews would begin demolishing the existing bridge. Working around the clock, new beams and precast bridge deck sections were installed and temporary precast barrier and parapet walls were put in place. The bridge would reopen to traffic in time for Monday morning commuter traffic.
“Coordinating with all parties and having the interstate opened to traffic on Monday at 6am was the biggest challenge,” said Lia Obaid, TDOT Construction assistant director.

The following weekend, or sometimes overnight during the week, the final finishing would be done to the bridge, including slipforming the permanent barrier and parapet walls. That’s where Irwin’s team came in, joining its first ABC project.

“If you can go in there and demo a bridge and put it back and have traffic back on it in 48 hours, you’re doing a pretty big thing,” said Irwin’s superintendent Stonie Garton.

Irwin’s crew poured approximately 914m of 890mm side parapet and 813mm high median barrier for the newly-constructed bridges with its 5700-C.

“It was a really fast-paced and accelerated job,” said Garton. “You have no choice but to stay on schedule. There is no option to not finish on time at any phase of the project. We had some weather challenges but there was no room for failure at all.”

With good planning and a lot of hard work from groups like Irwin’s, the US$62-million Fast Fix project was completed in only 6 months with only 10 weekend closures instead of 13. That was seven months ahead of schedule.

“We received very positive feedback from the road users, communities, and businesses,” TDOT’s Obaid said. “Without the use of ABC, this project would have taken at least two years or more.”

Advances in roadbuilding technology, including slipformed barrier, have changed the way DOTs approach large-scale projects. “It improves site constructability, total project delivery time, and work zone safety,” explained Obaid.

As for the Irwin team, being part of such a tightly scheduled project meant there was no room for machine breakdowns on the job.

“The machine performed perfectly,” said Garton. “There was never any issue with the machine and production and what we knew we could get done at any point in that job.”

He added that had the firm used traditional handforming methods to construct the walls, keeping pace with the tight timeframe would have been impossible.

For more information on companies in this article

Related Content

  • Granite pilots Volvo’s Compact Assist to new heights in Sacramento
    November 9, 2017
    While not required for its Sacramento Airport contract, Granite Construction* is getting to grips with IC specifications thanks to Volvo CE’s Compact Assist. In the US, 23 states have written intelligent compaction (IC) specifications for asphalt paving jobs and more states are expected to follow. Among those states with IC specs is California.
  • Zipping up road lanes – with Barrier Systems
    September 10, 2018
    QMB has a Lindsay Road Zipper on duty near Montreal. World Highways deputy editor David Arminas climbed aboard As vice president of Canadian barrier specialist QMB, based in Laval, Quebec, Marc-Andre Seguin is sanguine about the future for moveable barriers. On the one hand, it looks good. The oft-stated advantage of moveable barriers is that the systems are cheaper to install than adding a lane or two to a highway or bridge. Directional changes to lanes can boost volume on a road without disrupting tra
  • Bertha readies for more Seattle SR99 Alaskan Way Viaduct tunnel work
    July 27, 2015
    Bertha, one of the world’s largest tunnelling machines will resume work underneath the US city of Seattle in November, nearly two years after breaking down. Bertha, at 17.4m diameter, began her journey in July 2013. She was boring a path to relocate a 3.2km stretch of the elevated State Route 99 Alaskan Way Viaduct, built between 1949 and 1953 and which carries around 100,000 vehicles daily. The elevated section will be moved underground allowing the creation of public space along Seattle’s downtown w
  • Concrete surface for runway paving job
    January 18, 2016
    The Fort Lauderdale-Hollywood International Airport in Broward County, Florida, was suffering departure delays on every single flight. The existing 9R-27L runway was too short at 1615m in length, affecting capacity at the airport. To deal with the issue, the Broward County Board of County Commissioners created a plan to extend the southern runway to 2438m to accommodate larger commercial aircraft. The project was not simple however and could not be achieved by tearing out the existing runway and buil