Concrete pumps speed busy road upgrade

Work on a major upgrade at a busy German road junction is expected to be completed by the end of 2011. To assist in the project, two Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city.
May 3, 2012 Read time: 3 mins
Concreting is carried out with traffic flowing freely under the bridge construction. The Putzmeister M 58-5 pump is seen on the north-eastern ramp during construction
Work on a major upgrade at a busy German road junction is expected to be completed by the end of 2011.

To assist in the project, two 1259 Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city.

The junction, when viewed from above, looks like a flatly pressed four-leaf clover, and can no longer cope with traffic volumes. Two national motorways, the A 9 and the A 92, intersect at the junction, and along with the Munich motorway ring road (A 99) and the A 8 Ulm-Munich-Salzburg, the A 9 is the most important north-south route, especially for domestic and international commercial and holiday traffic.

The A 92 connects Munich with its airport and is also important for Eastern European traffic.

The average volume of traffic from the airport towards Munich is currently approximately 24,000/day, with the average daily traffic flow predicted to increase to about 38,000/day by 2020, meaning some 1,600 vehicles/hour using the Neufahrn junction, along with rush-hour traffic.

In view of this projection, the only option is a speedy connection via the existing motorway junction using a direct ramp. The current singlelane exit via a quadrant of the clover is being completely replaced by a two-lane flyover to channel traffic from the A 92 to the A 9 towards the south.

The customer is Autobahndirektion Südbayern and the contractor is Hentschke Bau in Bautzen.

Construction work at the junction started in April 2009 with the reconstruction of a connecting ramp and the spillage that is required to build the new bridge, with 110,000m³ of delivered soil. In 2010, comprehensive excavation and ceiling work took place at the Neufahrn junction as well as bridge construction work in the whole area.

At the flyover, concreting of the first 120m section was completed in October, 2010, and this was followed by the 80m-long section two scaffolding work carried out at night.

Each of the two Putzmeister truck-mounted concrete pumps was fully-supported at the foot of one of the construction columns within one of the northern clover quadrants of the motorway junction. From this location, they pumped concrete to the concrete placement sites on the approximately 12m high bridge, while traffic flowed freely on the circular paths of the exits and under the structure.

Concreting started at 6am, with the two truck-mounted concrete pumps standing fullysupported at the foot of one of the construction columns within one of the northern clover quadrants of the motorway junction. From this location, they pump concrete to the sites of concrete placement on the approx. 12m high bridge.

Meanwhile, the traffic flows freely on the circular paths of the exits and under the structure.

The complete superstructure contains 3,400m³ of concrete, and so that traffic can travel on the road comfortably and safely, the finished concrete surface receives another 8cm thick layer to the overall construction.

The concrete is first primed and completely sealed using epoxy resin. An asphalt sheeting (0.5cm) comes next and then a protective layer of mastic asphalt (3.5cm thick). Finally, the surface of the road is formed by a 4cm surface layer of stone mastic asphalt.

For more information on companies in this article

Related Content

  • Fast, cost-effective road stabilisation
    February 15, 2012
    The Kivikko industrial area in Finland, which is owned by the City of Helsinki, has expanded gradually over the years and it has expanded again with the new stabilised area now about 3.5hectares. The ALLU equipment and system was used to stabilise Kivikko for the first time in 2001, and the latest job started in June 2010 with the stabilisation work completed by mid-December 2010. [The ALLU Stabilisation System is a Finnish invention that provides a fast, cost-effective and environmental-friendly working
  • Putzmeister widening concrete pump range
    March 7, 2016
    Putzmeister’s BSF 47.5 truck-mounted pump is the lightest in its class according to the firm. Weighing less than 32tonnes, the new machine is mounted on a four axle truck and is equipped with a five section boom featuring the firm’s z-fold system. Said to be economical to operate and highly stable with its boom unfolded, the new machine meets the latest European emissions regulations. Tough and durable wear-resistant components, many of which are maintenance-free, the pump will give a long working life and
  • Putzmeister widening concrete pump range
    January 6, 2017
    Putzmeister’s BSF 47.5 truck-mounted pump is the lightest in its class according to the firm. Weighing less than 32tonnes, the new machine is mounted on a four axle truck and is equipped with a five section boom featuring the firm’s z-fold system. Said to be economical to operate and highly stable with its boom unfolded, the new machine meets the latest European emissions regulations. Tough and durable wear-resistant components, many of which are maintenance-free, the pump will give a long working life and
  • Tunnelling challenge on German project
    June 13, 2012
    A massive construction project has been underway deep in the heart of the Schnecktal valley area in Germany. From the surface, though, you would never be able to tell. The majority of the work is underground, as a joint-venture team led by German contractor Wayss and Freytag Ingenieurbau builds the nearly 7km long Finne Tunnel. After a few years of tunnel boring operations, the contractor is at work finishing the interior of the tunnel, slipforming first the tunnel’s floor and then a walkway with its GOMACO