U.S National Guard’s airport upgrade

In Kansas, specialist contractor Pavers has carried out important work for the National Guard. The aim of the work was to rehabilitate a WWII era hangar apron for the Kansas National Guard. The project required extensive repair work, including pavement patching, dowel bar retrofitting, partial depth patching and joint sealing. Pavers had to overhaul a 305m x 91.5m apron at Army Aviation Support Facility No 2 that suffered from poor drainage. The project included milling 152mm of old asphalt and concrete and
October 12, 2012 Read time: 3 mins
In order to keep on the tight schedule, contractor pavers needed to drill two lanes at a time and more than 32,000 holes were required

In Kansas, specialist contractor Pavers has carried out important work for the National Guard. The aim of the work was to rehabilitate a WWII era hangar apron for the Kansas National Guard. The project required extensive repair work, including pavement patching, dowel bar retrofitting, partial depth patching and joint sealing. Pavers had to overhaul a 305m x 91.5m apron at Army Aviation Support Facility No 2 that suffered from poor drainage. The project included milling 152mm of old asphalt and concrete and replace it with a fresh concrete overlay.

The company has plenty of experience in airport paving and repair work in Kansas and the Salina airport project for the National Guard had the company facing 610mm of concrete and asphalt. The scope of the project meant sharing responsibilities with other contractors. One contractor did the milling for the top 152mm of old concrete and asphalt that needed to come out, while another company was needed to install a 25.4mm thick asphalt bond separation layer. A third major subcontractor provided traffic control, installing barriers around the work area, and doing striping. Pavers focused on the drilling, doweling and concrete overlay work.

For the dowel drilling work Pavers used pneumatic equipment from Oklahoma-based 2976 E-Z Drill. Two slab rider drills helped speed along the Kansas National Guard project. When Pavers set to work with a crew of about 15-18 employees to reconstruct the apron for the Guard, it divided the 27,870m2 tarmac area near the hangar into 18, 4.88m-wide lanes, along with a few smaller areas. The company drilled more than 32,000 holes to complete the work, with about 875 holes for each lane edge. In just a day and a half, Pavers was able to finish four 305m -long edges, a very high productivity rate. The process consisted of the crew pouring two lanes at a time, then coming back to drill the edges on both before moving to the next lanes.

Pavers employed the E-Z Drill Model 210B-2 SRA, a two-gang slab rider drill, and the Model 210B-3 SRA, a three-gang version, to drill the thousands of 2.22mm diameter, 457mm deep holes needed for the project. Once Pavers had each lane’s holes drilled, it epoxied the dowels into place and finished off the lane with fresh concrete.

Having the right equipment and experience had Pavers completing the project in time — and getting the Kansas Guard fully operational again. The facility is now used for 10 helicopter pads for the Kansas Army National Guard’s UH-60 Black Hawk helicopters. A thicker concrete area allows heavier transport planes, such as the National Guard’s KC-135 refuelling aircraft when required.

For more information on companies in this article

Related Content

  • Researchers trial 3D printing for both concrete and asphalt roads
    February 27, 2019
    Automated road repairs, using 3D printing, could save money and vastly reduce disruption, and researchers are already showing it’s possible - Kristina Smith reports It’s the middle of the night, and in the street below a team is busy carrying out repairs to the road surface. But there isn’t a human in sight. A road repair drone has landed at the site of a crack and a 3D asphalt printer is now busy filling in that crack. A group of traffic cone drones have positioned themselves around the repair location
  • Bridge surface repair improves safety
    July 9, 2012
    Modern products are making life easier for those who have to look after bridges in need of repair Aproject to repair a bridge in the American state of Tennessee has brought safety benefits and improved the ride quality for drivers using the crossing. The Chickasaw Bridge spans the Ellington Parkway and it has benefited from a rehabilitation job by contractor Jamieson Construction. The roadway on the bridge was in a poor state and required frequent patching, and to tackle the problem, the Tennessee DOT consi
  • Indian airport revamp sets record
    September 2, 2022
    The use of machines from Dynapac has helped deliver upgrade work at Ahmedabad Airport in India, while setting production records
  • Florida road repaving delivers better surfacing
    April 7, 2017
    Paving the road for Florida’s latest mega project is the job of Volvo CE equipped concrete and asphalt specialist Ajax Paving Industries. Florida’s Gulf Coast provides a strong draw for tourists and residents alike, with coastal cities like North Port featuring a humid subtropical climate, beaches and resorts. But beyond the city’s sandy beaches, the streets of North Port had fallen into disrepair, causing transportation troubles.