U.S National Guard’s airport upgrade

In Kansas, specialist contractor Pavers has carried out important work for the National Guard. The aim of the work was to rehabilitate a WWII era hangar apron for the Kansas National Guard. The project required extensive repair work, including pavement patching, dowel bar retrofitting, partial depth patching and joint sealing. Pavers had to overhaul a 305m x 91.5m apron at Army Aviation Support Facility No 2 that suffered from poor drainage. The project included milling 152mm of old asphalt and concrete and
October 12, 2012 Read time: 3 mins
In order to keep on the tight schedule, contractor pavers needed to drill two lanes at a time and more than 32,000 holes were required

In Kansas, specialist contractor Pavers has carried out important work for the National Guard. The aim of the work was to rehabilitate a WWII era hangar apron for the Kansas National Guard. The project required extensive repair work, including pavement patching, dowel bar retrofitting, partial depth patching and joint sealing. Pavers had to overhaul a 305m x 91.5m apron at Army Aviation Support Facility No 2 that suffered from poor drainage. The project included milling 152mm of old asphalt and concrete and replace it with a fresh concrete overlay.

The company has plenty of experience in airport paving and repair work in Kansas and the Salina airport project for the National Guard had the company facing 610mm of concrete and asphalt. The scope of the project meant sharing responsibilities with other contractors. One contractor did the milling for the top 152mm of old concrete and asphalt that needed to come out, while another company was needed to install a 25.4mm thick asphalt bond separation layer. A third major subcontractor provided traffic control, installing barriers around the work area, and doing striping. Pavers focused on the drilling, doweling and concrete overlay work.

For the dowel drilling work Pavers used pneumatic equipment from Oklahoma-based 2976 E-Z Drill. Two slab rider drills helped speed along the Kansas National Guard project. When Pavers set to work with a crew of about 15-18 employees to reconstruct the apron for the Guard, it divided the 27,870m2 tarmac area near the hangar into 18, 4.88m-wide lanes, along with a few smaller areas. The company drilled more than 32,000 holes to complete the work, with about 875 holes for each lane edge. In just a day and a half, Pavers was able to finish four 305m -long edges, a very high productivity rate. The process consisted of the crew pouring two lanes at a time, then coming back to drill the edges on both before moving to the next lanes.

Pavers employed the E-Z Drill Model 210B-2 SRA, a two-gang slab rider drill, and the Model 210B-3 SRA, a three-gang version, to drill the thousands of 2.22mm diameter, 457mm deep holes needed for the project. Once Pavers had each lane’s holes drilled, it epoxied the dowels into place and finished off the lane with fresh concrete.

Having the right equipment and experience had Pavers completing the project in time — and getting the Kansas Guard fully operational again. The facility is now used for 10 helicopter pads for the Kansas Army National Guard’s UH-60 Black Hawk helicopters. A thicker concrete area allows heavier transport planes, such as the National Guard’s KC-135 refuelling aircraft when required.

For more information on companies in this article

Related Content

  • Recycling concrete runway saves time, money
    February 17, 2012
    Nashville International Airport in the US state of Tennessee has revamped its facilities following extensive upgrades being carried out on its oldest runway in a project worth some US$23 million. The airport authorities realised that to improve both capacity and safety a major improvement of runway 2L-20R was required, with full-depth reconstruction needed to provide the necessary structural strength and working life. Engineering firm Garver Aviation worked on the project to rehabilitate the portion of Runw
  • Terex built for bridge paving
    November 29, 2012
    To meet a need to carry out complex modern bridge designs, the Terex Bid-Well 3600 paver is available with truss transition inserts, increasing maximum paving width from 27.4-33.5m. The inserts adjust truss depth from 914-1219mm toward the paver’s centre, reducing frame deflection and this is said to increase surface profile smoothness. Offering paving widths from 4.6-33.5m with optional transition inserts, the 3600 gives companies more versatility for paving a wide variety of bridge designs, including mult
  • Rural Czech roads get paving upgrade
    November 2, 2012
    A series of rural road rebuilds have improved transport connections in the Czech Republic, helping to boost connectivity and the local economy The roads around Brandýs nad Labem, some 25km to the southwest of Czech capital Prague are crucial arteries to the rural and agricultural areas of the country. An assessment by regional authorities indicated that these roads are in need of repair. That led to cold planing and paving work on a series of rural roads near Brandýs nad Labem. The regional authorities had
  • Australia’s new airport in Queensland
    August 18, 2015
    The first new airport constructed in Australia for 45 years is now open for business. The Brisbane West Wellcamp Airport in Queensland is located 17km to the west of Toowomba. The facility was completed at the end of last year by Wagners, an Australian family-owned construction company. Toowoomba lies in the Darling Downs region of Queensland, located 126km west of Queensland’s capital city, Brisbane. Toowoomba’s population of approximately 165,000 makes it Australia’s second-most populous inland city. T