In Kansas, specialist contractor Pavers has carried out important work for the National Guard. The aim of the work was to rehabilitate a WWII era hangar apron for the Kansas National Guard. The project required extensive repair work, including pavement patching, dowel bar retrofitting, partial depth patching and joint sealing. Pavers had to overhaul a 305m x 91.5m apron at Army Aviation Support Facility No 2 that suffered from poor drainage. The project included milling 152mm of old asphalt and concrete and
October 12, 2012 Read time: 3 mins
In order to keep on the tight schedule, contractor pavers needed to drill two lanes at a time and more than 32,000 holes were required

In Kansas, specialist contractor Pavers has carried out important work for the National Guard. The aim of the work was to rehabilitate a WWII era hangar apron for the Kansas National Guard. The project required extensive repair work, including pavement patching, dowel bar retrofitting, partial depth patching and joint sealing. Pavers had to overhaul a 305m x 91.5m apron at Army Aviation Support Facility No 2 that suffered from poor drainage. The project included milling 152mm of old asphalt and concrete and replace it with a fresh concrete overlay.

The company has plenty of experience in airport paving and repair work in Kansas and the Salina airport project for the National Guard had the company facing 610mm of concrete and asphalt. The scope of the project meant sharing responsibilities with other contractors. One contractor did the milling for the top 152mm of old concrete and asphalt that needed to come out, while another company was needed to install a 25.4mm thick asphalt bond separation layer. A third major subcontractor provided traffic control, installing barriers around the work area, and doing striping. Pavers focused on the drilling, doweling and concrete overlay work.

For the dowel drilling work Pavers used pneumatic equipment from Oklahoma-based 2976 E-Z Drill. Two slab rider drills helped speed along the Kansas National Guard project. When Pavers set to work with a crew of about 15-18 employees to reconstruct the apron for the Guard, it divided the 27,870m2 tarmac area near the hangar into 18, 4.88m-wide lanes, along with a few smaller areas. The company drilled more than 32,000 holes to complete the work, with about 875 holes for each lane edge. In just a day and a half, Pavers was able to finish four 305m -long edges, a very high productivity rate. The process consisted of the crew pouring two lanes at a time, then coming back to drill the edges on both before moving to the next lanes.

Pavers employed the E-Z Drill Model 210B-2 SRA, a two-gang slab rider drill, and the Model 210B-3 SRA, a three-gang version, to drill the thousands of 2.22mm diameter, 457mm deep holes needed for the project. Once Pavers had each lane’s holes drilled, it epoxied the dowels into place and finished off the lane with fresh concrete.

Having the right equipment and experience had Pavers completing the project in time — and getting the Kansas Guard fully operational again. The facility is now used for 10 helicopter pads for the Kansas Army National Guard’s UH-60 Black Hawk helicopters. A thicker concrete area allows heavier transport planes, such as the National Guard’s KC-135 refuelling aircraft when required.

For more information on companies in this article

Related Content

  • Rolling out new and improved concrete pavers
    February 10, 2012
    Paver innovations The manufacturers are also rolling out several new and improved concrete paving models, with versatility and adaptability high on the agenda. GOMACO is now offering a novel independent IDBI attachment that allows dowel bar insertion behind a paver to form the transverse joint. The IDBI attachment is a new generation bar insertion system.
  • Innovations are pushing boundaries in the concrete road paving sector
    February 18, 2013
    The concrete road paving market continues to develop - Mike Woof reports Concrete road paving technology continues to evolve, with new equipment and techniques coming to market. Although concrete road construction has been used for many years, problems with early generation technologies affected this market segment. The first concrete roads were constructed in sections, which led to problems at joints but these were addressed many years ago with the advent of slipform paving. Concrete roads constructed in t
  • Developments in asphalt compaction machines
    July 4, 2012
    Mike Woof reviews the latest compaction market developments In the run-up to the upcoming World of Asphalt event in Orlando, Florida in March, the leading compaction equipment firms are rolling out upgraded and improved machines. With market conditions tough worldwide, customers are also likely to be encouraged with competitive deals on purchasing new machines and replacing ageing fleets.
  • Granite pilots Volvo’s Compact Assist to new heights in Sacramento
    November 9, 2017
    While not required for its Sacramento Airport contract, Granite Construction* is getting to grips with IC specifications thanks to Volvo CE’s Compact Assist. In the US, 23 states have written intelligent compaction (IC) specifications for asphalt paving jobs and more states are expected to follow. Among those states with IC specs is California.