US highway rebuild uses hard-wearing asphalt

Guntert & Zimmerman equipment is being used to create a new hard-wearing asphalt surface on a key Interstate highway in the US state of Kansas as Mike Woof reports A busy Interstate highway in the US is now benefiting from a new, long-lasting surface. The road, Interstate 70 in Western Kansas, was in need of resurfacing. The full-depth asphalt roadway, up to 508mm thick in certain sections, had reached the end of its working life.
July 18, 2012 Read time: 4 mins
Using concrete Koss has been able to provide a hard-wearing, long lasting surface on key connections in Kansas

Guntert & Zimmerman equipment is being used to create a new hard-wearing asphalt surface on a key Interstate highway in the US state of Kansas as Mike Woof reports

A busy Interstate highway in the US is now benefiting from a new, long-lasting surface. The road, Interstate 70 in Western Kansas, was in need of resurfacing. The full-depth asphalt roadway, up to 508mm thick in certain sections, had reached the end of its working life.

Resurfacing work had lasted just five to seven years and a longer term solution was required, according to Andrew Gisi, a geotechnical engineer with the Kansas DOT. The state opted for a 152mm bonded concrete overlay, some 121 million m2 of it in all. During 2011 6243 Koss Construction milled out the roadway to a depth of 152mm and slipformed two areas with concrete along some 24km of four-lane interstate.

Including shoulders, the two projects totalled 606,000m2 and the resurfacing cost some $20.1 million. The Kansas DOT is continuing with the I-70 upgrade and by the end of 2012, Koss will have milled and paved two more similar projects on I-70 for a total of 607,772m2 at a cost of $21.9 million.

The contractor has achieved good performance for its surface smoothness, winning incentives for every job it carried out in Kansas in 2011. The company also won an award from the Missouri-Kansas Chapter of the American Concrete Pavement Association (ACPA) for a 1372m section on which the contractor hit just 137mm of deviation.

Kansas DOT used Colorado’s pavement design criteria and system in designing its 152mm overlay on asphalt. With this technique, the overlay is sawn into panels that are 1.83m square and surfaces of this type have so far provided Colorado with 10-12 years of wear life on routes carrying heavy traffic, and remain in service.

Gisi says that Kansas expects to get 20 years from this overlay, possibly with some panel replacement at mid-life. He said, “The road really needed reconstruction, but we couldn’t afford that.”

Meanwhile Koss explained that the firm achieves good smoothness numbers on all of its contracts and added that it is easier to achieve low smoothness numbers on the thinner 152mm pavement, because the paver is not pushing a big head of material. “You can push the small head of mud and you are not extruding a lot of concrete either,” said Robert Kennedy, quality control manager for Koss.

Kennedy explained that the firm used dual stringlines. “We pay a lot of attention to the stringlines to make sure they are set up right and that our concrete batch plant is right. Then when we are confident that all of those things are set up, you have to be consistent,” he said. “The plant has to give you consistent slump on the concrete in every single batch after batch. And you have to have consistent delivery so that the paver never stops. Everything has to be in unison, working together.”

On a good day, Kennedy said Koss paved 1.6km a day, working 9.14m wide. “We averaged about 1505m2 per hour, or maybe a little better,” he said. Two belt placers spread concrete in front of the paver, and that helped boost production. That way, Koss could dump two trucks at once. Each project last year had its own batch plant, and typically 15 trucks hauled concrete to the site.

For nearly 3.2km of pavement last year, Koss paved with a stringless automated control system from 265 Leica Geosystems. The automatic paver control system bases its guidance on a digital terrain model, a digitised 3D model of the pavement loaded into an on-board computer. The paver also has two prisms, mounted above the machine and which provide a reference for the machine location for the two robotic total stations set up on tripods ahead of the paver. The prisms on the paver have a relation to points on the concrete paver’s pan.

Koss used three robotic total stations, and set two of them 76m in front of the paver. One robotic total station was set behind. When the paver advanced close to the two forward stations, a technician would leapfrog the rear total station to a point up ahead.

Kennedy said one advantage to the milling and concrete overlay process was that Koss could correct roadway slopes and transitions into and out of curves. With so many asphalt treatments over 40 years, the slopes had gone awry. “We could go in there and pave back to the exact slope and correct all of those geometric issues,” Kennedy said.

For more information on companies in this article

Related Content

  • Bitumen technology suppliers seek new ways to save money and work more efficiently
    April 24, 2013
    When World Highways decided to ask some of the industry’s leading suppliers what the future holds for bitumen, we found out - not surprisingly in the current economic climate - that it’s all about saving money. Kristina Smith reports. How quickly the tide turns. Just two years ago, saving carbon and the planet was moving up many countries’ political agendas. Now politicians in Europe and beyond have been forced to park commitments in the face of economic austerity. “The big issue with local government is th
  • G&Z paving Canada’s longest runway
    October 12, 2012
    A contractor in Canada, Dufferin Construction, is using three items of new equipment bought from Guntert & Zimmerman to pave the country’s longest runway. The project is extensive, featuring a new runway measuring 4.3km long by 60m wide, an apron area measuring 145,000m2 and two taxiways, each 3.8km long by 25m wide. In all, the work requires 1.5 million tonnes of base aggregate, and 200,000m2 of cement-stabilised base. Dufferin Construction Company, a division of Holcim (Canada) already owns two other G&Z
  • Machine control advances boosting quality
    June 12, 2017
    The latest developments in machine control technology will deliver major gains in quality and productivity. Machine control technology plays an increasingly important role in construction. The pace of development has been fast, with new systems offering major gains in both productivity and quality across a range of applications. At the recent CONEXPO-CON/AGG 2017 exhibition in Las Vegas, key advances were unveiled in machine control technologies suited to markets such as earthmoving, concrete paving and pil
  • Hamburg-Finkenwerder airport has new runway surface
    August 21, 2013
    Hamburg’s Finkenwerder airport is now benefiting from a new runway surface following work carried out by contractor KEMNA BAU. The company recently used machines from Dynapac to resurface 36,000m2 of the runway track in Hamburg-Finkenwerder, a facility used by Airbus. The airport handles around 10-15 take-offs and landings/day when aircraft are either undergoing flight testing or being delivered to customers, as well as for deliveries of components by transport aircraft. The project was tricky as the