US highway rebuild uses hard-wearing asphalt

Guntert & Zimmerman equipment is being used to create a new hard-wearing asphalt surface on a key Interstate highway in the US state of Kansas as Mike Woof reports A busy Interstate highway in the US is now benefiting from a new, long-lasting surface. The road, Interstate 70 in Western Kansas, was in need of resurfacing. The full-depth asphalt roadway, up to 508mm thick in certain sections, had reached the end of its working life.
July 18, 2012 Read time: 4 mins
Using concrete Koss has been able to provide a hard-wearing, long lasting surface on key connections in Kansas

Guntert & Zimmerman equipment is being used to create a new hard-wearing asphalt surface on a key Interstate highway in the US state of Kansas as Mike Woof reports

A busy Interstate highway in the US is now benefiting from a new, long-lasting surface. The road, Interstate 70 in Western Kansas, was in need of resurfacing. The full-depth asphalt roadway, up to 508mm thick in certain sections, had reached the end of its working life.

Resurfacing work had lasted just five to seven years and a longer term solution was required, according to Andrew Gisi, a geotechnical engineer with the Kansas DOT. The state opted for a 152mm bonded concrete overlay, some 121 million m2 of it in all. During 2011 6243 Koss Construction milled out the roadway to a depth of 152mm and slipformed two areas with concrete along some 24km of four-lane interstate.

Including shoulders, the two projects totalled 606,000m2 and the resurfacing cost some $20.1 million. The Kansas DOT is continuing with the I-70 upgrade and by the end of 2012, Koss will have milled and paved two more similar projects on I-70 for a total of 607,772m2 at a cost of $21.9 million.

The contractor has achieved good performance for its surface smoothness, winning incentives for every job it carried out in Kansas in 2011. The company also won an award from the Missouri-Kansas Chapter of the American Concrete Pavement Association (ACPA) for a 1372m section on which the contractor hit just 137mm of deviation.

Kansas DOT used Colorado’s pavement design criteria and system in designing its 152mm overlay on asphalt. With this technique, the overlay is sawn into panels that are 1.83m square and surfaces of this type have so far provided Colorado with 10-12 years of wear life on routes carrying heavy traffic, and remain in service.

Gisi says that Kansas expects to get 20 years from this overlay, possibly with some panel replacement at mid-life. He said, “The road really needed reconstruction, but we couldn’t afford that.”

Meanwhile Koss explained that the firm achieves good smoothness numbers on all of its contracts and added that it is easier to achieve low smoothness numbers on the thinner 152mm pavement, because the paver is not pushing a big head of material. “You can push the small head of mud and you are not extruding a lot of concrete either,” said Robert Kennedy, quality control manager for Koss.

Kennedy explained that the firm used dual stringlines. “We pay a lot of attention to the stringlines to make sure they are set up right and that our concrete batch plant is right. Then when we are confident that all of those things are set up, you have to be consistent,” he said. “The plant has to give you consistent slump on the concrete in every single batch after batch. And you have to have consistent delivery so that the paver never stops. Everything has to be in unison, working together.”

On a good day, Kennedy said Koss paved 1.6km a day, working 9.14m wide. “We averaged about 1505m2 per hour, or maybe a little better,” he said. Two belt placers spread concrete in front of the paver, and that helped boost production. That way, Koss could dump two trucks at once. Each project last year had its own batch plant, and typically 15 trucks hauled concrete to the site.

For nearly 3.2km of pavement last year, Koss paved with a stringless automated control system from 265 Leica Geosystems. The automatic paver control system bases its guidance on a digital terrain model, a digitised 3D model of the pavement loaded into an on-board computer. The paver also has two prisms, mounted above the machine and which provide a reference for the machine location for the two robotic total stations set up on tripods ahead of the paver. The prisms on the paver have a relation to points on the concrete paver’s pan.

Koss used three robotic total stations, and set two of them 76m in front of the paver. One robotic total station was set behind. When the paver advanced close to the two forward stations, a technician would leapfrog the rear total station to a point up ahead.

Kennedy said one advantage to the milling and concrete overlay process was that Koss could correct roadway slopes and transitions into and out of curves. With so many asphalt treatments over 40 years, the slopes had gone awry. “We could go in there and pave back to the exact slope and correct all of those geometric issues,” Kennedy said.

For more information on companies in this article

Related Content

  • Building Egypt's world class Desert Highway
    April 13, 2012
    A huge highway upgrade project will transform the Cairo-Alexandria road link into a world-class connection as Mike Woof reports. The work to upgrade the Desert Highway connecting Egypt's sprawling capital Cairo with its major port Alexandria, is one of the country's largest infrastructure projects for many years. This 220km highway link is being widened and improved to cope with the hugely increased traffic volumes resulting partly from Egypt's fast growing vehicle population. The Egyptian economy is strong
  • Concrete paving key to Berlin's airport runways
    February 17, 2012
    High production concrete paving is proving a key feature at the new Berlin airport facility currently under construction The new Berlin-Brandenburg International Airport will soon provide improved links by air to the city. Work started in mid 2006 with the redevelopment of the existing Berlin Schönefeld Airport.
  • GPS machine control paves the way for Turkish canal
    February 7, 2012
    GPS machine control for earthworks and concrete paving is helping to fast track construction of an irrigation canal in Turkey - Claire Symes reports. The Turkish economy is expected to flourish as a result of construction of a new irrigation channel currently underway in the east of the country. This canal is benefiting from the latest concrete paving and earthmoving technology and will bring with it prosperity to a deprived area of the country. But the project is already taking the lead in terms of Turkish
  • Spanish contractor Sorigué has the edge with VÖGELE SprayJet
    March 21, 2016
    Spanish contractor Sorigué, the first to use the SUPER 1800-3i SprayJet from Vögele, has pioneered paving thin overlays and the development of new mixes. The company won the contract for rehabilitating the surface course of the 3km-long dam, 10m-wide promenade in the Catalonian port city of Tarragona. Sorigué’s idea was to overlay the existing surfacing with a thin layer applied to a spray seal of polymer-modified bitumen. The spray seal prevents water penetrating inside the structure – a major advant