Novel concrete paving method used in Germany

A novel dual-layer concrete paving technique has been used on jobsites in Germany on the country’s high-speed Autobahn network This technique allows the construction of a strong and durable roadway structure able to cope with heavy traffic loads and offer a long working life. In four German states, Wirtgen SP-1500 slipformers have been employed by four different contractors to carry out dual-layer paving. The method allows a noise-reducing, non-skid exposed aggregate surface to be placed over a bottom
January 25, 2017 Read time: 5 mins
Dual layer slipforming techniques have been used to rebuild key Autobahn links in Germany
A novel dual-layer concrete paving technique has been used on jobsites in Germany on the country’s high-speed Autobahn network

This technique allows the construction of a strong and durable roadway structure able to cope with heavy traffic loads and offer a long working life. In four German states, 2395 Wirtgen SP-1500 slipformers have been employed by four different contractors to carry out dual-layer paving.

The method allows a noise-reducing, non-skid exposed aggregate surface to be placed over a bottom-layer of structural concrete. The high-grade subbase offers a high load-bearing capacity and is normally 200–240mm thick. This is overlaid with a 50-80mm thick top layer of exposed aggregate concrete.

Slipform paving is used to place the two concrete grades, wet-on-wet. The compressive strength, bending tensile strength and indirect tensile strength are the same for both the bottom layer and the top but the composition of the concrete differs. While around 350kg cement/m³ is used in the bottom-layer, 420kg cement/m³ is required in the exposed aggregate concrete.

Coarse aggregate is important in the top layer and only double broken and double screened chippings with high angularity, grain shape and resistance to polishing are used. This ensures that the concrete surfacing retains its noise-reducing and skid-resistance properties as well as its long term durability.

When the two layers of concrete have been paved, a surface retarding agent is applied to the freshly smoothed surface by a texture curing machine (TCM). Depending on the weather, the coarse aggregate is exposed by brooming the surface after placing the concrete, providing the required non-skid surface with that has profile peaks and a texture lowering tyre noise.

Four German projects have used this technique, with three to rebuild 30-40 year old concrete roads and a fourth to reconstruct a stretch suffering from alkali-silica reaction (ASR).
One project was for a 4.5km rehabilitation of the A1 near Trier by 8553 Berger Bau, another was for a 2.3km improvement of the A5 near Karlsruhe by Bickhardt Bau and a third for a 5.3km rebuild of the A1 near Lübeck by 3281 Eurovia Beton. The fourth was for a 4.8km improvement of a section of the A9 with ASR near Weissenfels by 8554 Max Bögl

On the A1, Berger Bau used the SP 1500 to pave a 200mm-thick bottom-layer concrete pavement with 360kg cement/m³ concrete and a maximum aggregate size of 22. Meanwhile, the 60mm-thick top-layer concrete comprised a high-grade material mix with 420kg cement/m³ concrete and double broken and double screened chippings.

But material logistics presents a challenge as two different concrete grades are required at the same time. The bottom-layer concrete is dumped directly in front of the paver, while the top-layer concrete is delivered to the second machine by a conveyor. The concrete is either filled directly from the truck into a material hopper or intermediate container, while conveyors with chutes at the end dump the top-layer onto the compacted bottom-layer.

For its job on the A9, Max Bögl used 45 articulated trucks carrying from 6,500-7,000tonnes of sand, gravel and chippings/day during the paving phase, in addition to 27 trainloads of cement. Rebuilding the highway meant managing a complex system of machines, material, weather, ambient conditions and personnel.

For this method, the bottom-layer paver is equipped with dowel bar and tie bar inserters, while the top-layer paver uses a finishing beam and super smoother to produce a level surface. The pavers feature an intelligent control system to optimise quality, with a TCM providing the finish.

Dowel bars and tie bars are inserted in the pre-compacted wet concrete at freely determined intervals by the automatic integrated dowel bar and tie bar inserter. Because the dowel bar inserter can move in the direction of paving, it can remain in position over the transverse joint until the vibratory insertion process is complete, while the slipform paver continues to advance.
In these projects, the dowel bars were positioned in the middle of the finished concrete surfacing, at intervals of 140-150mm, as specified. A closed, even and homogeneous surface was assured by a finishing beam and super smoother integrated in the top-layer paver.

So that roadways can be paved with accuracy, three of the four contractors use sensors to adjust the height of the front metering screed. These continuously measure the filling level of the concrete in the compaction zone and adjust the height of the front metering screed, ensuring that the correct quantity of material is delivered.

Curing is important when paving exposed aggregate concrete. For these jobs, a combination of surface retarding agent and dispersion is applied to the finished and smoothed surface in precise quantities. The retarding agent delays the setting and initial hardening of the concrete surface for a limited time, while the dispersion prevents the surface from drying out and cracking. As soon as the concrete has cured sufficiently to be driven over, the surface is brushed to expose the coarse aggregate and an additional dispersion is applied to the brushed surface. Exposing the coarse aggregate gives the concrete pavement its important non-skid properties.

For more information on companies in this article

Related Content

  • Vögele sets paving record in German capital
    September 16, 2015
    Material transfer vehicles and remixing systems are crucial to delivering quality paving. Using material transfer vehicles (MTVs) can play a major role in delivering high quality road surfaces. These units can help boost quality by minimising the risk of material or thermal segregation. A major road paving project has been carried out in Germany using innovative paving methods. For the first time ever, binder and surface courses were paved over a width of 15.5m. This paving job was carried out on a 4.2km st
  • New machines boost concrete paving performance and accuracy
    July 21, 2015
    New concrete paving machines offer greater versatility as well as performance – Mike Woof writes GOMACO said that its Next Generation Commander III paver has been designed to increase safety and all-round visibility, while offering improved performance. This four track paver benefits from the firm’s latest G+ Connect technology as well as 3D guidance options. A key to the improved performance is the G+ control system while the machine also has power from a quiet, low-emission Tier 4 engine. Fuel consumption
  • Rainforest road repair and rehabilitation with stabilisation
    May 23, 2014
    A limited amount of aggregate and resources, including fuel, in the Riau province of Indonesia can challenge roadbuilders, but Indonesian contractor PT Harap Panjang overcame the obstacles on a recent project. The province rests in a tropical rainforest. The 2600mm of annual rainfall take a toll on the area’s roads, particularly those developed by oil company Chevron Pacific Indonesia. The remote roads were built to service Chevron operations, crucial to the economies of the city, region and country. The r
  • Vögele demonstrates spray system
    February 28, 2012
    Vögele expects to find new customers for its latest Sprayjet system following successful demonstrations to UK contractors. The SprayJet machine was used to repair a busy road in Ipswich, in eastern England, placing the tack coat and asphalt surface in a single pass.