Improved runway facility for Florida’s Fort Lauderdale Airport

Florida’s Fort Lauderdale- Hollywood International Airport (FLL) is now benefiting from an upgraded runway. A key portion of the work has been carried out using equipment from Minnich. The airport handles about 23 million passengers/year and with about 3 million of those from international flights, there was a need to develop the facility to cope with the larger aircraft used on international flights. The Broward County Aviation Department was responsible for the work and specified that the runway exp
August 18, 2015 Read time: 3 mins
The Minnich machine can be controlled remotely, allowing the operator to stand at a safe distance while also allowing good views of the working area
Florida’s Fort Lauderdale- Hollywood International Airport (FLL) is now benefiting from an upgraded runway. A key portion of the work has been carried out using equipment from Minnich.

The airport handles about 23 million passengers/year and with about 3 million of those from international flights, there was a need to develop the facility to cope with the larger aircraft used on international flights.

The Broward County Aviation Department was responsible for the work and specified that the runway expansion would cover approximately 407,190m2 of concrete. To handle the work, 4760 Archer Western Construction was awarded the project for the paving of FLL’s 10R28L runway.

The expansion of runway 10R28L included several challenges. The 2423 Federal Aviation Administration (FAA) mandated that the new south runway be ready for aircraft use by the third quarter of 2014. In addition, the airport needed to remain fully functional during the expansion process.

The budget for Archer Western’s portion of the renovation was about US$87 million. The runway-paving contract was part of a larger expansion, including two bridge structures and an embankment to elevate the new runway over US-1 and the FEC Railway lines.

An integral part in the concrete paving process was reinforcing and aligning the concrete slabs with dowel pins. Once a concrete slab cures, dowel-pin holes are drilled in the sides of the slab, and dowel pins are inserted into the holes. At that point, the crew can pour the adjacent slab of concrete, and it will ensure that the slabs are properly aligned and reinforced. The runway expansion project required approximately 172,000 dowel-pin holes to be drilled and the contractor required a productive piece of equipment to complete this process.

Archer Western chose the 286 Minnich A-4SCW (four-gang, self-propelled, wireless) dowel-pin drill, equipped with the optional dust collection system. The Minnich A-4SCW proved to be a valuable companion throughout the process, drilling four holes at a time. By attaching the A-4SCW to a portable air compressor, the crew was able to drive the unit along the slab while standing at a safe distance.

Archer Western equipped the unit with Minnich’s optional dust collection kit, a dust collection system using a vacuum attached to each of the drills that minimises dust and debris and reduces clean-up times. This improved safety both for the airport environment and also for the crew.

The firm also chose the Minnich machine because it is self-propelled and can be controlled remotely, keeping the operator at a safe distance, while also allowing accurate hole-spotting.

On site the crew averaged about 30 seconds to drill four holes using the Minnich machine, which met with the productivity requirements of the tight working schedule.

For more information on companies in this article

Related Content

  • Runway rebuild for key Bulgarian airport
    August 21, 2013
    Varna Airport in north-east Bulgaria provides an important international link for the country, with a runway rebuild helping improve capacity. The airport is of particular importance for Bulgaria’s tourist trade as it provides a major connection for visitors to the Black Sea coast. And the reconstruction work at Varna Airport’s only runway will ensure the facility is able to handle the area’s increasing visitor numbers. The project had to be carried out quickly and efficiently to prevent delays to f
  • Tough competition in concrete paving market
    February 13, 2012
    One thing is clear in the concrete slipforming sector. This comparatively niche market for equipment is rapidly becoming a good deal more competitive as key manufacturers jostle for position.
  • Paving a Japanese airport within strict time constraints
    September 19, 2012
    In Japan, major efforts are being made to both conserve energy and materials, while also delivering high quality airport runways. At Haneda Airport, as well as at the Fukuoka, Chitose and Sendai airports, innovative use is being made of asphalt paving equipment from Sumitomo. The latest model HA60W J paver from Sumitomo is being used to lay warm mix asphalt, while the contractors is also using sophisticated control technology. To minimise disruption to flight schedules, construction work at Haneda has been
  • Meeting the challenge of desert runway resurfacing
    February 8, 2012
    Ferocious daytime temperatures can provide a tough challenge to construction firms working in desert conditions in Egypt's south. Despite the high daytime temperatures however, Egyptian contractor Orascom has managed to complete an airport project on budget and ahead of schedule, while meeting the client's tight specifications.