A contractor in Canada, Dufferin Construction, is using three items of new equipment bought from Guntert & Zimmerman to pave the country’s longest runway. The project is extensive, featuring a new runway measuring 4.3km long by 60m wide, an apron area measuring 145,000m2 and two taxiways, each 3.8km long by 25m wide. In all, the work requires 1.5 million tonnes of base aggregate, and 200,000m2 of cement-stabilised base. Dufferin Construction Company, a division of Holcim (Canada) already owns two other G&Z
October 12, 2012 Read time: 3 mins

A contractor in Canada, Dufferin Construction, is using three items of new equipment bought from Guntert & Zimmerman to pave the country’s longest runway. The project is extensive, featuring a new runway measuring 4.3km long by 60m wide, an apron area measuring 145,000m2 and two taxiways, each 3.8km long by 25m wide. In all, the work requires 1.5 million tonnes of base aggregate, and 200,000m2 of cement-stabilised base.

6695 Dufferin Construction Company, a division of 2813 Holcim (Canada) already owns two other G&Z pavers, and added an S1500 four-track Slipform Paver, a PS1200 Placer Spreader, and a TC1500 Texture Cure Machine to its fleet for this project. The project is at Calgary International Airport in Alberta, where Dufferin’s contract calls for more than 1 million m2 of new concrete surface. Construction has started and Dufferin is working through two construction seasons – 2012 and 2013 – to complete the work, which is scheduled to wrap up by May 2014.

According to project superintendent Mike Cristinziano, one challenge is to place and pave the sheer volume of aggregates and concrete required. “You need to take into consideration that our construction season up here in Calgary is not as long as in other parts of the country,” said Cristinziano. “Depending on the weather, our season runs from May or June until October, and that’s it.” The weather is a major factor in the operation, with the construction team prepared to work around the clock, and seven days a week, in order to finish on time, according to John Zavarella, superintendent of concrete plants and equipment for Dufferin.

The concrete for runways and taxiways will be 435mm thick, while the apron concrete will be 415mm.

The firm bought its first G&Z paver, an S1500, in 1995 when it was working on Highway 407 in Ontario and later added an S850 to the fleet. Zavarella said, “When we were looking at the Calgary site, it called for paving 12.5m at the widest, and we have already tackled airport jobs of that width with that type of pavement.”

Cristinziano said Dufferin is using two pavers – the S1500 and the S850 – on the Calgary airport project, with the S850 handling narrower widths and shorter stretches of pavement.

Several features of the G&Z machines come in useful for Dufferin’s needs. The paver has split guillotine side gates that allow it to back onto existing slabs at the start of the day, while reducing the need for handwork. The new TeleEndXL telescopic end section allows quick width changes between 12.5m and 10m, which are frequent for this project. All three machines – the paver, the placer and the texture cure machine – have 90° steering capability, boosting their manoeuvrability. Because of this feature, each machine can turn the tracks 90° and move directly across to the next slab, reducing set up time. The PS1200 allows Dufferin to place dowel baskets well out in front of the paving train. And the placer spreader also has a 1.626m belt that slides in and out and allows Dufferin to place concrete faster and more efficiently.

For more information on companies in this article

Related Content

  • Concrete paving advance in the market
    December 9, 2022
    New concrete paving technology is now coming to market from Wirtgen, with the firm broadening its product range with new and improved models now available
  • Airport runway rebuild at Bologna
    May 15, 2019
    Rebuilding a runway requires special attention to detail to maximise efficiency and safety Airport runways face special challenges with regard to the loads they carry on a daily basis, particularly when aircraft are landing. A modern jet aircraft will typically land at speeds of around 240-260km/h, with a laden 747 weighing as much as 265tonnes at the end of a long flight. The stresses these large aircraft place on runway surfaces are enormous and not just with the massive impact forces exerted during
  • G&Z’s new S850SL paver
    January 10, 2013
    Guntert & Zimmerman (G&Z) has launched its S850SL mid-size slipform paver with swing legs. The firm said that following its domestic and international market success with the G&Z S600, the patented AccuSteer: Slew Drive Track Control System and SmartLeg: Swing Leg System have been made available as options on the G&Z S850SL in lieu of the reliable and time-tested QUADRA bolster system. AccuSteer consists of slew drives that are mounted on top of the crawler track yokes that are used to steer the tracks in l
  • Redevelopments at southern Polish airports
    August 21, 2013
    Rzeszów-Jasionka Airport in the south-east of Poland is now benefiting from a new taxiway constructed over a 50-month period and costing some €22.5 million. The work was required as the airport needs to increase capacity to cope with growing passenger traffic. The main portion of the project was for the construction of a 3km long taxiway, which lies parallel to the airport’s main runway. This taxiway now allows aircraft to manoeuvre away from the single runway and free up capacity for take-offs and land