Efficient concrete overlays

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay. Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage. CFI has slipformed most of the overlays with its GOMACO two-track GP-2600 paver. This season, the co
February 15, 2012 Read time: 2 mins
Efficient concrete overlays are being achieved with the use of stringless controls

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay.

Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage.

CFI has slipformed most of the overlays with its 218 Gomaco two-track GP-2600 paver. This season, the company added the Leica Geosystems stringless system and a new GOMACO four-track GHP-2800 paver to the inventory. Both were put to work on the project near Osage.

The new unbonded concrete overlay is 6.7m wide, and the material is placed directly on the existing asphalt surface of the roadway. The surface only has to be swept clean before the mix is dumped on it and concrete slump averages around 13-25mm.

The firm has seen increased production with fewer people needed for stringline maintenance and setup. Five site personnel who normally worked with the stringline are now used elsewhere during the paving process. The lack of stringline also allows them to focus more on quality and production rather than stringline maintenance.

The GOMACO GHP-2800 is pulling burlap for a burlap drag finish behind the paver. Finishers work behind the paver with bull floats before a texture/cure machine applies a longitudinal tine and white spray cure.

For more information on companies in this article

Related Content

  • Vögele introduces new spray paver
    January 6, 2017
    Vögele is introducing a new generation SprayJet model, built around its latest Super 1800-3i asphalt paver. Like its predecessor, the new machine features an add-on emulsion tank and spraybars and is designed to both spray emulsion and carry out asphalt paving. Anja Sehr of the firm’s marketing and communications department said, “This does two steps in one.” She added that using this type machine boosts paving quality, as the SprayJet can ensure a homogenous layer of emulsion is spread over the surface, be
  • Wirtgen introducing new concrete paver range
    March 3, 2015
    Wirtgen is introducing a new concrete paver range, the SP90 series. These models will replace the existing SP80 series as well as the SP850. Four basic models have been announced at present, the SP92, SP92i, SP94 and SP94i, although with the range of options and features available, the capabilities offered will be extensive. Paving widths for the machines now range from 2-9.5m, increasing the maximum width and allowing these units to handle a wider array of slipforming tasks than the earlier SP80 Series mod
  • A special smooth road surface
    August 12, 2022
    Contractor Tarmac has delivered a high- quality finish for a novel underground automotive test track.
  • Vögele sets paving record in German capital
    September 16, 2015
    Material transfer vehicles and remixing systems are crucial to delivering quality paving. Using material transfer vehicles (MTVs) can play a major role in delivering high quality road surfaces. These units can help boost quality by minimising the risk of material or thermal segregation. A major road paving project has been carried out in Germany using innovative paving methods. For the first time ever, binder and surface courses were paved over a width of 15.5m. This paving job was carried out on a 4.2km st