Efficient concrete overlays

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay. Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage. CFI has slipformed most of the overlays with its GOMACO two-track GP-2600 paver. This season, the co
February 15, 2012 Read time: 2 mins
Efficient concrete overlays are being achieved with the use of stringless controls

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay.

Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage.

CFI has slipformed most of the overlays with its 218 Gomaco two-track GP-2600 paver. This season, the company added the Leica Geosystems stringless system and a new GOMACO four-track GHP-2800 paver to the inventory. Both were put to work on the project near Osage.

The new unbonded concrete overlay is 6.7m wide, and the material is placed directly on the existing asphalt surface of the roadway. The surface only has to be swept clean before the mix is dumped on it and concrete slump averages around 13-25mm.

The firm has seen increased production with fewer people needed for stringline maintenance and setup. Five site personnel who normally worked with the stringline are now used elsewhere during the paving process. The lack of stringline also allows them to focus more on quality and production rather than stringline maintenance.

The GOMACO GHP-2800 is pulling burlap for a burlap drag finish behind the paver. Finishers work behind the paver with bull floats before a texture/cure machine applies a longitudinal tine and white spray cure.

For more information on companies in this article

Related Content

  • GOMACO has updated its sophisticated G+ control system
    January 6, 2017
    The G+ Connect is GOMACO’s latest proprietary CAN-based network products allowing fast, two-way communication between all accessories and the G+ controller. This closed-loop control system for the electronics and hydraulics links the paver’s valves and various sensors and delivers high accuracy. The system is said to allow tighter, faster, and more accurate machine corrections and improves communications between components for precision setup and paving. The G+ Connect uses the G+ control system and GOMACO’
  • GOMACO has updated its sophisticated G+ control system
    January 28, 2013
    The G+ Connect is GOMACO’s latest proprietary CAN-based network products allowing fast, two-way communication between all accessories and the G+ controller. This closed-loop control system for the electronics and hydraulics links the paver’s valves and various sensors and delivers high accuracy. The system is said to allow tighter, faster, and more accurate machine corrections and improves communications between components for precision setup and paving. The G+ Connect uses the G+ control system and GOMACO’
  • Millimetre accuracy for concrete paving
    July 30, 2019
    Concrete paving is now benefiting from the use of sophisticated machine control tools to deliver accuracy and high-quality surfaces Heavy use of concrete roads and runways over time will reveal any flaws in workmanship, the invasion of water, or the wear from use. Discolouration, scaling, crazing, cracking, or curling will sometimes occur due to a poor ready-mix batch, inadequate curing procedure, subgrade settlement, or improper bonding of the finish layer. Concrete surfaces are generally very durab
  • Micro surfacing the Brooklyn Bridge with Bergkamps’ M210 paver
    May 16, 2018
    A major job for micro surfacing took place on the Brooklyn Bridge near New York. It was the third time in Ken Messina’s career that he would provide micro surfacing for the iconic Brooklyn Bridge, built in 1883. Messina, as president of New Jersey-based Asphalt Paving Systems (APS), knew only too well the challenges that lay ahead. And there were many. There would be only a brief window of opportunity for paving, with lane closures starting at 10pm and ending at 5am. The cool, humid atmosphere would a