Efficient concrete overlays

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay. Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage. CFI has slipformed most of the overlays with its GOMACO two-track GP-2600 paver. This season, the co
February 15, 2012 Read time: 2 mins
Efficient concrete overlays are being achieved with the use of stringless controls

Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay.

Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage.

CFI has slipformed most of the overlays with its 218 Gomaco two-track GP-2600 paver. This season, the company added the Leica Geosystems stringless system and a new GOMACO four-track GHP-2800 paver to the inventory. Both were put to work on the project near Osage.

The new unbonded concrete overlay is 6.7m wide, and the material is placed directly on the existing asphalt surface of the roadway. The surface only has to be swept clean before the mix is dumped on it and concrete slump averages around 13-25mm.

The firm has seen increased production with fewer people needed for stringline maintenance and setup. Five site personnel who normally worked with the stringline are now used elsewhere during the paving process. The lack of stringline also allows them to focus more on quality and production rather than stringline maintenance.

The GOMACO GHP-2800 is pulling burlap for a burlap drag finish behind the paver. Finishers work behind the paver with bull floats before a texture/cure machine applies a longitudinal tine and white spray cure.

For more information on companies in this article

Related Content

  • New Holland 'space savers'
    February 15, 2012
    Zero tailswing excavators from New Holland are part of a plant deal won by civil engineering contractor K Rouse with Balfour Beatty. The machines, 11 E135BSRs and two smaller models, the E80 and E50, are being used on a section of the M621 motorway near the city of Leeds, northern England, to remove existing metal crash barriers and install improved drainage prior to the erection of a new concrete central reservation.
  • Twin layer paving evolves
    November 2, 2012
    Dual layer paving offers benefits to wear life as well as major cost reductions - Mike Woof reports The concept of laying the binder course and wearing course at the same time is not new to the road construction market. Various contractors have been working on systems over a number of years, with several manufacturers helping directly with these projects. A number of firms have investigated this method but three manufacturers in particular, Dynapac and Vögele in Europe and Sumitomo in Japan, have made major
  • Astec’s Azerbaijan asphalt application
    June 9, 2015
    In Azerbaijan an Astec batching plant is said to be giving a major contractor an advantage over its competition The firm, Aztikintiyol, is one of the leading producers of aggregates and hot-mix asphalt in Azerbaijan and decided to expand its operations into the southern regions of the country. The need for asphalt in this area was growing as there is massive infrastructure development close to the border with neighbouring Iran taking place. However a simple plant was not suitable as the firm required
  • Naylor drains away waste water concerns
    January 26, 2017
    A bespoke waste water drainage system saved time and money on a recent UK motorway scheme Work on the London’s M25 motorway Junction 30/A13 Corridor Relieving Congestion Scheme is being undertaken by joint venture contractor Balfour Beatty/Skanska. The project is valued at nearly €91 million and completion is for autumn 2016. There has been a successful continual programme of clean-up using road-sweeper/gulley cleaning trucks to remove detritus from the works areas. Disposal of this type of waste w