Skip to main content

Concrete paving job for Wirtgen machines in Nigeria

Concrete paving equipment from Wirtgen has been used to slipform a concrete road surface in south-west Nigeria Anew concrete roadway connects the towns of Itori und Ibese in Nigeria’s Ogun State. The construction work has been carried out by AG-Dangote Construction Company and made use of the sophisticated technology offered by Wirtgen’s SP 500 slipform paver. For this project, the contractor, a joint venture between the Brazilian company Andrade Gutierrez Company and the Dangote Group from Nigeria, rel
May 14, 2018 Read time: 5 mins
Dangote has built the longest stretch of concrete road in Nigeria
Concrete paving equipment from Wirtgen has been used to slipform a concrete road surface in south-west Nigeria

A new concrete roadway connects the towns of Itori und Ibese in Nigeria’s Ogun State. The construction work has been carried out by AG-8506 Dangote Construction Company and made use of the sophisticated technology offered by 2395 Wirtgen’s SP 500 slipform paver.

For this project, the contractor, a joint venture between the Brazilian company 1339 Andrade Gutierrez Company and the Dangote Group from Nigeria, relied above all on a Wirtgen slipform paver in an inset application.

For the inset application, the concrete is either deposited right in front of the slipform paver or is fed in front of the machine from the side via a belt conveyor or side feeder. In the next step, the concrete is distributed evenly across the full paving width by a spreading auger or spreading plough. Integrated electrical or hydraulic vibrators ensure homogeneous compaction of the concrete. The inset mold forms the concrete slab to the specified thickness and width while the slipform paver advances. In addition, a dowel bar inserter can be integrated which inserts the dowel bars into the concrete as specified parallel to the paver’s direction of travel. Central tie bars or side tie bars can be inserted transverse to the concrete pavement. The surface is levelled off transverse to the paver’s direction of travel by the finishing beam. The grinding movement produces a small concrete roll in front of the beam which boosts the quality of the concrete surface. In the next step, a super smoother, oscillating in
a combination of lateral and longitudinal movements, ensures the final surface accuracy. Wirtgen texture curing machines such as the 2833 TCM 95 or TCM 180 can then be used to deliver the desired surface structure, applying a dispersion to the concrete surface which prevents the surface and edges from drying too quickly.

This is the longest concrete roadway in Nigeria. But before the slipform paver was able to begin work in Itori, the substrate first had to be prepared. The construction company used compacted laterite and a 200mm layer of crushed rock. “The SP 500 then paved the concrete quickly and cost-efficiently. At the same time, it also helps us ensure that our production quality meets the specifications for surface evenness," explained Ashif Juma, managing director of AG-Dangote Construction Company Limited. The SP 500 laid down the new 7.5m-wide and 200mm-thick roadway in two separate passes. Extending over 24km, the new road is the longest uninterrupted stretch of concrete roadway in Nigeria.
To continuously provide the concrete paver with sufficient material, a steady convoy of up to 15 concrete-mixing trucks drove to the job site, depositing their loads directly in front of the machine. However, before concrete can be paved, it must first be produced. The production chain begins with limestone mining. This mineral is one of the raw materials used in cement, which in turn forms the basis of concrete. The Dangote Group extracts limestone from its quarry in Ibese, where the Dangote Cement Company operates 14 Wirtgen 2500 SM surface miners.


The Wirtgen surface miners cut, crush and load the rock in one single operation. The rock is broken down directly during the extraction process into grain sizes that are suitable for belt conveyors, making the use of a crusher superfluous. This saves time and reduces the costs of the entire mining process. Wirtgen had already supported the Dangote Group before operations at the Ibese facility began, not only with the machinery, but also with production process planning and training for the specialists on site. This partnership has now endured for more than 15 years. It therefore stood to reason that AG-Dangote Construction Company Limited would opt to use Wirtgen technology and applications know-how for the road construction project between Itori and Ibese.

“The SP 500 not only ensured that construction project processing went off without a hitch, but also produced a paving result that impressed both us and the client. We processed more than 35,000m³ of concrete using the Wirtgen slipform paver, and produced an even surface,” said Juma.

For example, the side tie bar inserter, which in Nigeria inserted 12mm-diameter tie bars into the sides of the pre-compacted concrete to securely connect the two adjacent roadways, can be selected as an equipment option with the SP 64/SP 64i. The new generation of slipform pavers combines the application diversity of the SP 500 Series with the sophisticated technology of the larger SP 90 Series.

Work on the 24km concrete roadway was completed after six months of construction. After completion of the paving work, a concrete cutting machine cut slits at right-angles into the road surface at intervals of 3.65m so that the resulting joints could be filled with expandable material. These predetermined breaking points prevent potential tension cracks. “With professional maintenance, this will ensure that the roadway lasts for at least 40 years," said Juma, explaining the last step of the construction procedure. The managing director also decided to acquire additional concrete equipment from Wirtgen. AG-Dangote Construction Company Limited has expanded its fleet of road construction machines, purchasing two of the last SP 500 pavers produced, along with a TCM 95 texture curing machine.

For more information on companies in this article

Related Content

  • Gomaco smooth the way for new NY State concrete highway
    April 2, 2014
    When New York State Thruway wanted to experiment with unbonded concrete overlays, they chose an 8km, four-lane section of Interstate 90 near Hamburg as their test section. Surianello General Concrete, based in Buffalo, New York, won the bid to pave the 22.9cm thick concrete overlay. The age and the design of the original roadway created a major paving challenge. It was built in the 1950s and didn’t conform to current geometry requirements for superhighways. “They built it with a standard crown sectio
  • Road recycling in Denmark
    May 13, 2024
    A novel approach to road refurbishment has saved time, money and carbon emissions in Denmark, while delivering a quality road surface.
  • Thin surface whitetopping for busy roads
    April 5, 2017
    In the US, considerable experience has been gained with thin white-topping (TWT), with the technique now being used in other countries as well. In the US hundreds of km of TWT is being paved every year, much of it across the mid-western states. A variation of white-topping is being used in Oregon to replace badly rutted asphalt truck lanes on primarily long uphill grades with durable, continuously reinforced concrete pavement (CRCP). Oregon has carried out several of these concrete inlay projects over the
  • Key Nigeria port road resurfacing work
    October 5, 2018
    Resurfacing of an important port road connection in Nigeria is now complete. The Apapa Wharf road provides a vital link to the busy port of Apapa, close to Nigeria’s commercial centre of Lagos in the south west of the country. The road has been in desperate need of repair as it had been badly worn due to heavy traffic volumes. The new road section has now been constructed from concrete in a bid to offer a long working life and to allow the route to cope better with the high percentage of heavily laden truck