Long-lasting surface repairs for Avonmouth Bridge

Two technologies combined to give a heavily used bridge a new surface that should last for years The Avonmouth Bridge carries the M5 motorway over the River Avon, and is a vital part of the road infrastructure in south-west England, linking the counties of Somerset, Devon and Cornwall to the rest of the country. Completed in 1973, it carries commuters to the city of Bristol, and to South Wales, along with holidaymakers. The 1.4km long steel box girder bridge comprising a 16,000m2 steel decked central span a
July 9, 2012 Read time: 4 mins
The Gussasphalt road surface: the paving machine ran on rails

Two technologies combined to give a heavily used bridge a new surface that should last for years

The Avonmouth Bridge carries the M5 motorway over the River Avon, and is a vital part of the road infrastructure in south-west England, linking the counties of Somerset, Devon and Cornwall to the rest of the country. Completed in 1973, it carries commuters to the city of Bristol, and to South Wales, along with holidaymakers.

The 1.4km long steel box girder bridge comprising a 16,000m2 steel decked central span and two 16,000m2 concrete approach spans is subject to significant vibration, which is increased by the 120,000 vehicles/day using the bridge. This wears the thin surfacing, and while it was resurfaced in 2000, in September 2006 it was decided the bridge should be resurfaced again.

InterRoute, the 2579 Mott MacDonald and 1146 Balfour Beatty Infrastructure Services joint venture, which is the 1441 UK Highways Agency managing agent for the region, awarded 2314 Stirling Lloyd the bridge deck waterproofing /resurfacing contract.   

This was the culmination of five years of collaborative development work between Cliff Weston, technical sales director of Stirling Lloyd, manufacturers of the Eliminator bridge deck waterproofing system; their preferred surfacing partner, Aeschlimann International, which supplies the advanced Gussasphalt surfacing system, and InterRoute.

Extensive planning and specific measures were taken to ensure that any impact on traffic was minimised, including keeping three lanes of traffic in both directions open at all times. It was also decided that with peak usage being in the summer months, the works would be carried out during winter (the southbound carriageway between September-December 2008, and the northbound carriageway over the same period in 2009).

In September 2008 Stirling Lloyd Construction's specialist surface preparation subcontractor began removing the existing surfacing and waterproofing from the southbound carriageway. This proved difficult as the previously applied Eliminator waterproofing had not deteriorated since it was applied and had maintained its strong bond to the substrate.

When removed and the next stage was to re-apply new Eliminator waterproofing. The durable, tough, liquid spray applied waterproofing membrane based on advanced MMA technology forms a seamless membrane, with no joints which could be susceptible to water penetration.  

The appropriate primer, ZED S94 anti-corrosive primer on the steel sections and PAR 1 reactive primer on the concrete deck, was applied to enhance the bond of the subsequent membrane and when this had cured, in under an hour, the membrane was applied in two colour-contrasting coats to provide a minimum dry film thickness (dft) of 2mm. Wet film gauge thickness tests taken throughout application to confirm this thickness was being achieved.

Once the first coat had cured and tested, a second 1mm dft layer of Eliminator was applied and overscattered with an aggregate before curing in order to provide additional resistance to shear in the surfacing. Finally a heat sensitive tack coat to enhance the bond between the membrane and the subsequent Gussasphalt surfacing was applied, a job sub-contracted to Aeschlimann International, specialists in the application of Gussasphalt surfacing.

Gussasphalt, a dense mastic asphalt that is itself almost impervious and is self-compacting when laid, is spread rather than laid using a special paving machine that runs on pre-positioned rails to achieve the required thicknesses of asphalt. This highly accurate process, having a tolerance of +/-2mm, provides an excellent ride quality and ensures that the deadweight is controlled since the depth of the asphalt pavement is accurately kept to the level prescribed by the bridge engineer. Applied to the entire 17m wide carriageway in two runs in order to minimise the number of joints, the total thickness of surfacing was only 50mm on the steel sections and 60mm on the concrete.

Having collaborated on a number of large projects, Stirling Lloyd knew the Eliminator system would forge an excellent bond to the Gussasphalt and that the final surface would produce an excellent ride quality.
Planning for refurbishment of the northbound carriageway using the same products and methodology is underway, and it is claimed that the new surface will reduce maintenance costs dramatically in the coming years.

For more information on companies in this article

Related Content

  • HA dismantles footbridge over M5 in England
    January 3, 2013
    Contractors worked solidly throughout the night during one Saturday and early Sunday morning in November (2012) to dismantle the Pegwell Brake footbridge over the M5 near Bristol, south west England. The concrete footbridge, located between junctions 16 and 17, needed to be demolished to make way for a new steel pedestrian bridge suitable for high-sided vehicles to pass under when the managed motorway is fully operational and the hard shoulder is used as a running lane. The dismantling and removal of the
  • Protecting new asphalt overlay
    October 20, 2017
    Techniques can help in preventing cracks in underlying layers from penetrating to new surface layers - *Farzad Tooryani. For road repairs involving milling off worn asphalt surface layers before repaving, the use of crack sealing is a crucial task. This can help to prevent full reflection of existing cracks from underneath layers into the new wearing course. Once the milling work is complete, locating existing cracks is a crucial task for the site supervisor. Efficient routing equipment that is easy to hand
  • Sssshhhhhh! - quiet concrete on UK trial
    January 14, 2025
    Tarmac is testing quiet concrete in the UK
  • More on the Newmarket Viaduct replacement
    June 15, 2012
    When it was completed in 1965 – just six years after the Auckland Harbour Bridge – the six-lane Newmarket Viaduct with its tall, slender piers was something of an engineering wonder, the first of its kind in the Southern Hemisphere. Forty years on it had become a much-maligned contributor to Auckland’s chronic traffic congestion, too weak seismically to withstand the heaviest loaded trucks let alone a severe earthquake, so narrow in the shoulders that any accident stopped traffic flow and made it difficult