Asphalt plans silos increase efficiency, reduce waste

A Colombian contractor tackles specifications for asphalt road work with Astec equipment. Award-winning Colombian contractor MHC has upgraded its Astec Portable Double Barrel plant to handle highway and other projects. The plant, installed in Bucaramanga, equipped with two RAP [recycled asphalt pavement] bins, a Double Barrel Green System, and one New Generation silo was bought by MHC in 2009. It has now received a second silo and a truck scale extension.
March 21, 2012 Read time: 4 mins
MHC's Portable Double Barrel plant installed in Bucaramanga, Colombia

A Colombian contractor tackles specifications for asphalt road work with Astec equipment

Award-winning Colombian contractor MHC has upgraded its 1250 Astec Portable Double Barrel plant to handle highway and other projects.

The plant, installed in Bucaramanga, equipped with two RAP [recycled asphalt pavement] bins, a Double Barrel Green System, and one New Generation silo was bought by MHC in 2009. It has now received a second silo and a truck scale extension.

MHC is a USO 9001:2000 corporation presided over by Mario Huertas Cotes, and is a leading road contractor with headquarters in Colombia’s capital Bogota.

Established in 1975, it specialises in engineering and mining as well as dams, bridges, and heavy road construction using asphalt. On some of these roads MHC has remained as a concessionary partner with all maintenance operations.

In 1994, the company obtained the coveted National Engineering Prize for the Sesquile Dam, and it currently has two contracts with 2812 Invias (National Highway Institute).

One contract involves the rehabilitation and maintenance of roads located in Montería in the Department of Córdoba with a mix use of 15,000tonnes per month at an elevation of 305m above sea level.

One of the issues relating to the contract was the procurement of aggregates, which led the contractor to use limestone with “great results.”

The second contract was for the study, design, land use, social, environmental, and construction aspects of a 205km long, four-lane highway between Bucaramanga and Cúcuta in the Department of 4001 Santander.

The main issue with this project was obtaining the land to install the asphalt plant and crushing equipment. The end result was installing the Astec equipment in the limestone quarry at Surata outside the city of Bucaramanga.
According to president Mario Huertas, the Astec plant was the best solution to guarantee a permanent and ready supply of hot mix while meeting the contractor's specifications.

 “The delivered product is very homogenous and the plant is well below the local environmental gas emissions standards and calories (heat) emissions to the atmosphere,” he explained.

“The 95% uptime and safety features of the plant have greatly contributed to an overall cost reduction in production.”
He also noted the reduction in the cost of consumables, burner fuel and a reduction in the oxidation of the daily mix production.
Huertas praised the innovation of the Astec equipment when it came to the Double Barrel Green System and New Generation storage silos.

“The Green System added to the Double Barrel drum mixer allows me to reduce fuel consumption and increase production. The warm mix asphalt does not need the addition of expensive commercial additives: using water with the mix along with the liquid asphalt cement is all that is needed.

“We are able to store mix in the Astec New Generation HMA [hot mix asphalt] storage silo for four days without the loss of mix quality.”

By keeping the silo full, the plant is always ready to meet customer demand; equipment efficiency is maximised and material waste is reduced.

In storage mode, the silos are completely sealed at the top and the bottom to prevent oxidation.

“I have become convinced that silos allow you to increase daily production with a substantial reduction in operational costs for the mix made on the previous day, which allows a better and more efficient use of human resources to mix transport trucks to feed the road works,” said Huertas.”

To date, MHC has three 2987 Telsmith aggregate classifiers (Model 2561T); two impact crushers (Model FT4240); one vertical axis impact crusher 2500; one Astec Mobile Screens model PTSC (Model 3618Vm), and one ProSizer (Model 2612V).

“The relationship with Astec is a partnership that goes beyond basic customer service,” acclaimed Huertas.
“The Astec Group knows its products; knows how to relate the technologies to my applications, and knows how to provide excellence in customer service. This is evident through all Astec divisions and the people that represent the company, including our Colombia Astec agent, Rodriguez and Londono.”

Meeting the standards required by MHC's customers is not a problem, according to Huertas, who said Astec listened to his technical and business suggestions, thus allowing him to purchase equipment to provide better production, a reduced maintenance cost, and a better mix quality to his operations.

“In terms of service, Astec has been very effective, receptive, timely, and very experienced. With the conditions in Colombia, we need a good response on parts for routine maintenance.

“Astec has maintained the added value with its customers through its post-sale relationship between local agents and end customers.”

For more information on companies in this article

Related Content

  • Ammann asphalt plant supplies material in China
    May 16, 2018
    An Ammann asphalt plant has been used to supply material for a landmark project in China. The Ammann ABP 320 Universal Asphalt-Mixing Plant played an important role in carrying out preparation work for the high-profile BRICS Summit held recently in China
  • Innovative asphalt plant for German contractor
    September 24, 2018
    A German contractor is now using the innovative BA RPP 4000 asphalt mixing plant from Benninghoven to boost efficiency. The firm, Max Bögl, is using the plant at its Sengenthal site, to supply material to road construction projects in the Nuremberg region. A key feature of the plant is the hot gas generator with counterflow parallel drum system, which allows high RAP content and minimal emissions. The plant supplies some 2,000tonnes/day of hot mix to job sites across the region. Depending on the formula,
  • Asphalt plant inspection service from Astec
    July 19, 2017
    Astec Industries is now offering its Silobot inspection service for materials storage silos. The Silobot is a sophisticated tool that Astec’s parts department can use to carry out thorough visual inspection and metal thickness testing inside hot mix storage silos. The remote control capabilities of the Silobot inspection device ensure that personnel stay out of the confined space of the silos. The firm says that the unit can carry out inspections quicker, safer, and more thoroughly. The inspection record pr
  • LafargeHolcim delivers Algeria concrete road solution
    May 14, 2018
    In Algeria, LafargeHolcim has introduced roller compacted concrete (RCC) for the first time in the country to renovate the RN45 road, with reduced costs, construction time and increased durability - *Nicolas Miravalls. Heavy traffic on a road stretch in northern Algeria has resulted in the need for rebuilding of the link, making it better able to cope with demand. In Algeria’s Msila region, the RN 45 road carries over 700 heavy load trucks/day, 365 days/year and required a major re-construction. In 2017, La