Peab Asfalt of Sweden primarily handles major road and highway projects in the inland portion of the country, but the company was willing and able to take on a new challenge when an airport runway needed to be paved in its own backyard. The work was done in Jönköping, which has a relatively small airport but which is still crucial to the inland area of Sweden. Flights were typically rerouted during the project, with the exception of two per day in the late afternoon or evening. This enabled Peab Asfalt t
February 13, 2012 Read time: 4 mins
Peab Asfalt's Caterpillar AP600D paving at Jonkoping Airport
2593 Peab Asfalt of Sweden primarily handles major road and highway projects in the inland portion of the country, but the company was willing and able to take on a new challenge when an airport runway needed to be paved in its own backyard.

The work was done in Jönköping, which has a relatively small airport but which is still crucial to the inland area of Sweden.

Flights were typically rerouted during the project, with the exception of two per day in the late afternoon or evening. This enabled Peab Asfalt to make progress almost daily, and also kept outbound and inbound passengers and freight connecting to key hubs in the Swedish capital Stockholm and Copenhagen, Denmark.

"Even with the limited flights, we had to adjust paving schedules," said Reijo Seppanen, project superintendent for Peab Asfalt. Paving often started in the middle of the night and extended into the late afternoon of the following day.

Another contractor handled the first phase of the project, which consisted of milling about 50mm off the existing surface, and then the asphalt was laid. The paving portion of the project took about three weeks with the insulated trucks travelling about 70km from the asphalt plant to the airport.

Segregation is always on the mind of Seppanen and others at the company. The efforts start at the plant, with proper loading of the trucks, which have rounded, not flat- bed, bottoms. This prevents sticking when the materials are end-dumped into the 2294 CAT AP600D later in the process.

To help, during the work the traffic was light given the area and the fact that much of the paving was done at night. Shorter truck cycle times, combined with other segregation fighting efforts, paid off.

The mix left the plant at 170º-180ºC and was dumped into the hopper at about 160º-165ºC.

Plant production, paving speed and trucking were all calculated to keep the paver moving at a consistent pace.

"We move continuously. That's one of the key efforts we make to prevent segregation," said Seppanen.

Another segregation-fighting technique is allowing mix to collect in the sides of the hopper throughout the shift.

The Caterpillar AP600D was a newcomer to the site, with the company previously using a different manufacturer's product.

The Cat paver worked at a pace of about 4-5m/minute, placing a single lift of 40mm at a width of 4.5m. Ten passes were required to cover the entire width of the 45m runway.

"The middle of the runway is the highest point because of drainage. We started at one side, then made five passes until we reached the middle. Then we started at the opposite side, and worked our way back to the middle," said Seppanen.

The width of the project led to many longitudinal joints. Peab Asfalt crews placed the new, hot mat slightly higher than the adjacent cold mat. A breakdown compactor used a small side roller to compact the joint.

Three heavy rollers, in the 11tonne range, handled compaction.

The first roller made 6-7 passes, with a movement up being one pass, and the movement back counting as a second pass, while the second roller worked about 50m from the paver. The number of passes varied based on that day's conditions. The compactor was vibrating while making its passes.

The third roller had no set distance between it and the rest of the paving train.

Core samples were taken along the way to ensure adequate compaction was being achieved, and while the project had production and time demands, Peab Asfalt was glad to take it on.

"We don't have many projects like that come up. When there is an opportunity, you have to take advantage of it," said Seppanen, who emphasised the importance of product support for the company's efforts to hit deadlines and overcome other obstacles.

"It's important on time-sensitive jobs like this," said Seppanen.

For more information on companies in this article

Related Content

  • Bitumen technology suppliers seek new ways to save money and work more efficiently
    April 24, 2013
    When World Highways decided to ask some of the industry’s leading suppliers what the future holds for bitumen, we found out - not surprisingly in the current economic climate - that it’s all about saving money. Kristina Smith reports. How quickly the tide turns. Just two years ago, saving carbon and the planet was moving up many countries’ political agendas. Now politicians in Europe and beyond have been forced to park commitments in the face of economic austerity. “The big issue with local government is th
  • Italy's strategic tunnel link
    August 21, 2012
    The world's largest tunnelling machine is completing Italy's important road connection between Bologna and Florence - Adrian Greeman reports For just under a decade a huge programme of highway construction has been underway in the mountainous region between Bologna and Florence, realigning a section of the A1 highway nearly 70km long. The new section, through major tunnels and across high viaducts, will greatly increase capacity on Italy's most important highway.
  • G&Z pave the way as East meets West
    March 28, 2014
    The Silk Route is one of the oldest trading links between Europe and Asia and is being upgraded with some of the newest equipment. The nation of Georgia is located on what is known as the ‘crossroads’ between Western Asia and Eastern Europe. It lies to the east of the Black Sea and is on one of the shortest routes between western China and Europe. Since the Middle Ages this strategically important country has played host to one of the network of roads collectively known as the Silk Route. For much of the 20
  • Rising to the challenge
    July 18, 2012
    Visualise today's concept of a major commercial traffic corridor in the western United States. A roadway responsible for delivering goods to Arizona, Nevada and Utah, that also connects Mexico to the United States to Canada through the North American Free Trade Agreement (NAFTA). What springs to mind? A multi-lane highway carrying thousands of vehicles a day past cities at speeds up to 113km/hour, while egress ramps make sure vehicles get safely to city streets and their final destination. This is not the c