Swedish airport job for Cat

Peab Asfalt of Sweden primarily handles major road and highway projects in the inland portion of the country, but the company was willing and able to take on a new challenge when an airport runway needed to be paved in its own backyard. The work was done in Jönköping, which has a relatively small airport but which is still crucial to the inland area of Sweden. Flights were typically rerouted during the project, with the exception of two per day in the late afternoon or evening. This enabled Peab Asfalt t
February 13, 2012 Read time: 4 mins
Peab Asfalt's Caterpillar AP600D paving at Jonkoping Airport
2593 Peab Asfalt of Sweden primarily handles major road and highway projects in the inland portion of the country, but the company was willing and able to take on a new challenge when an airport runway needed to be paved in its own backyard.

The work was done in Jönköping, which has a relatively small airport but which is still crucial to the inland area of Sweden.

Flights were typically rerouted during the project, with the exception of two per day in the late afternoon or evening. This enabled Peab Asfalt to make progress almost daily, and also kept outbound and inbound passengers and freight connecting to key hubs in the Swedish capital Stockholm and Copenhagen, Denmark.

"Even with the limited flights, we had to adjust paving schedules," said Reijo Seppanen, project superintendent for Peab Asfalt. Paving often started in the middle of the night and extended into the late afternoon of the following day.

Another contractor handled the first phase of the project, which consisted of milling about 50mm off the existing surface, and then the asphalt was laid. The paving portion of the project took about three weeks with the insulated trucks travelling about 70km from the asphalt plant to the airport.

Segregation is always on the mind of Seppanen and others at the company. The efforts start at the plant, with proper loading of the trucks, which have rounded, not flat- bed, bottoms. This prevents sticking when the materials are end-dumped into the 2294 CAT AP600D later in the process.

To help, during the work the traffic was light given the area and the fact that much of the paving was done at night. Shorter truck cycle times, combined with other segregation fighting efforts, paid off.

The mix left the plant at 170º-180ºC and was dumped into the hopper at about 160º-165ºC.

Plant production, paving speed and trucking were all calculated to keep the paver moving at a consistent pace.

"We move continuously. That's one of the key efforts we make to prevent segregation," said Seppanen.

Another segregation-fighting technique is allowing mix to collect in the sides of the hopper throughout the shift.

The Caterpillar AP600D was a newcomer to the site, with the company previously using a different manufacturer's product.

The Cat paver worked at a pace of about 4-5m/minute, placing a single lift of 40mm at a width of 4.5m. Ten passes were required to cover the entire width of the 45m runway.

"The middle of the runway is the highest point because of drainage. We started at one side, then made five passes until we reached the middle. Then we started at the opposite side, and worked our way back to the middle," said Seppanen.

The width of the project led to many longitudinal joints. Peab Asfalt crews placed the new, hot mat slightly higher than the adjacent cold mat. A breakdown compactor used a small side roller to compact the joint.

Three heavy rollers, in the 11tonne range, handled compaction.

The first roller made 6-7 passes, with a movement up being one pass, and the movement back counting as a second pass, while the second roller worked about 50m from the paver. The number of passes varied based on that day's conditions. The compactor was vibrating while making its passes.

The third roller had no set distance between it and the rest of the paving train.

Core samples were taken along the way to ensure adequate compaction was being achieved, and while the project had production and time demands, Peab Asfalt was glad to take it on.

"We don't have many projects like that come up. When there is an opportunity, you have to take advantage of it," said Seppanen, who emphasised the importance of product support for the company's efforts to hit deadlines and overcome other obstacles.

"It's important on time-sensitive jobs like this," said Seppanen.

For more information on companies in this article

Related Content

  • Advanced concrete slipforming technology coming to market
    August 1, 2019
    New concrete slipforming technology is said to offer increased performance over earlier generation equipment - Mike Woof writes
  • LiuGong has major plans for future corporate development
    December 10, 2015
    LiuGong unveiled new machines as well as its plans for the future at the BICES 2015 construction equipment show in Beijing recently. Trading conditions are tough in China at the moment, but LiuGong is performing better financially than many of its local rivals according to the firm. LiuGong’s vice-president, Dave Beatenbough said that the firm is particularly well known for its wheeled loaders, a product line for which the firm is a market leader in China. However, he explained that the company is actively
  • New asphalt paving developments are coming to market
    January 7, 2015
    Atlas Copco introduces new low emission diesels in its latest large paver models - Mike Woof writes The large pavers from Atlas Copco’s Dynapac range are now compliant with the Tier 4 Final/Stage IV emissions regulations due to the installation of new engines. Running costs are also said to have been reduced due to lower fuel consumption and the firm claims each of the latest models can offer a fuel saving of 4200 litres/year, as well as a reduction in CO2 emissions of 11tonnes/year.
  • Controlling influence
    January 3, 2013
    New lane control solutions from major roadmarking companies have been installed on highways across the world over recent months. Guy Woodford reports on some of them. Clearview Traffic Group (CTG) recently clocked up the installation of over 70,000 Astucia active flush and surface mounted road studs in the UK. CTG has been involved in numerous road stud installation projects on motorways and other road types in the UK and many other countries worldwide. Its UK installations include over 4,500 Astucia road s