Asphalt milling key to runway upgrade project

Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city. The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point.
February 20, 2012 Read time: 2 mins
Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city.

The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point.

As part of the overall master plan for the modernisation of CSIA, Mumbai International Airport (MIAL) is completely reconstructing both the runways to create an efficient airside infrastructure, which is the core of an airport. It will bring the runways up to international standards in order to handle the larger Airbus A380s.

The primary runway work is scheduled for completion about now while the intersection between the two runways is closed for reconstruction for four hours, one day a week until March.

As part of the scheme 1144 Gmmco, India's largest 178 Caterpillar dealer, sealed a deal to sell the first new 2m PM200 cold planer in India to contractor 1145 Ashwini Infra Developments, which was hired to carry out the milling and asphalting of the secondary runway reconstruction project at the CSIA.

The crews are only able to complete the project during overnight hours and that "required tight planning and firm schedules. Any breakdown would result in the complete abandonment of plans." Ashwini Infra Developments already owned a Cat PM102, and its previous experience "made the decision to purchase the new PM200 easy." Ravi Goudar, director, AID, said: "Gmmco has been very supportive as a dealer and we are very happy with their service. Hence, when it came to choosing a bigger milling machine we went with a Caterpillar PM200."

For more information on companies in this article

Related Content

  • Zaxis-5s biggest-ever project
    January 27, 2014
    Norwegian contractor Carl C Fon has secured its largest-ever road construction contract to complete a 4.6km section of the E18 in the Mysen region of its home country. It started the €25million project in August 2012 and it is scheduled for completion in the summer of 2014.
  • New asphalt compaction technologies boost quality
    February 28, 2012
    More sophisticated compaction technologies are now coming to market, offering a wide range of benefits to users
  • New asphalt compaction technologies boost quality
    April 13, 2012
    More sophisticated compaction technologies are now coming to market, offering a wide range of benefits to users While asphalt paving techniques vary widely between North America and Europe, there is greater commonality in the compaction methods required. New developments in compaction rollers are offering contractors using both North American and European style paving techniques major gains in quality. According to Robert Horan, a regional engineer for the US-based Asphalt Institute, intelligent compact
  • Highway recycling in the US state of South Carolina
    February 17, 2021
    A highway stretch in the US state of South Carolina has benefited from the use of a recycling train to rebuild the road surface