Asphalt milling key to runway upgrade project

Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city. The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point.
February 20, 2012 Read time: 2 mins
Work is continuing to upgrade Chhatrapati Shivaji International Airport (CSIA), India's largest airport in Mumbai, the country's largest city.

The airport is equipped with a cross runway system (primary runway) and (secondary runway), with both intersecting each other at a common point.

As part of the overall master plan for the modernisation of CSIA, Mumbai International Airport (MIAL) is completely reconstructing both the runways to create an efficient airside infrastructure, which is the core of an airport. It will bring the runways up to international standards in order to handle the larger Airbus A380s.

The primary runway work is scheduled for completion about now while the intersection between the two runways is closed for reconstruction for four hours, one day a week until March.

As part of the scheme 1144 Gmmco, India's largest 178 Caterpillar dealer, sealed a deal to sell the first new 2m PM200 cold planer in India to contractor 1145 Ashwini Infra Developments, which was hired to carry out the milling and asphalting of the secondary runway reconstruction project at the CSIA.

The crews are only able to complete the project during overnight hours and that "required tight planning and firm schedules. Any breakdown would result in the complete abandonment of plans." Ashwini Infra Developments already owned a Cat PM102, and its previous experience "made the decision to purchase the new PM200 easy." Ravi Goudar, director, AID, said: "Gmmco has been very supportive as a dealer and we are very happy with their service. Hence, when it came to choosing a bigger milling machine we went with a Caterpillar PM200."

For more information on companies in this article

Related Content

  • Cold milling popular for road materials recycling
    March 2, 2012
    Milling techniques remain one of the most widely used recycling methods
  • THIS is a Paving Project– The I-15 CORE
    December 20, 2012
    Provo, Utah – The scope of the I-15 Corridor Expansion Project (I-15 CORE) in the state of Utah is nearly unprecedented because of the size of the project and the short completion deadline. Twenty-four miles (38.6 km) of removal and replacement of Interstate 15 between Lehi and Spanish Fork, widening the number of traveling lanes by two, for up to six lanes in each direction in 35 months. The new 364 lane miles (586 km) of concrete roadway will be slipformed 12 or 12.5 inches (305 or 318 mm) thick for a tot
  • Cold milling popular for road materials recycling
    July 4, 2012
    Milling techniques remain one of the most widely used recycling methods Well-proven, cold milling techniques remain one of the most widely used methods for materials recycling in road construction. Milled road materials can be cleaned up and re-used in both asphalt and concrete highway construction. German firm Wirtgen has long dominated the market for road milling machines and has the largest share of the sector (as well as the broadest product range), although other firms based in Europe and the US are be
  • Heavy work for Cat 730C Ejector Truck on English bypass
    December 18, 2017
    When Flannery Plant Hire was awarded work on the Norwich bypass project, they purchased a wide range of new Caterpillar machines. Caterpillar dealer Finning UK & Ireland supports construction of the Norwich Bypass, one of the UK’s largest road infrastructure projects, with a vast range of Caterpillar machines and advanced Caterpillar Production Management - CPM. Known as the Northern Distributor Road, the project is managed by primary contractor Balfour Beatty, with P. Flannery Plant Hire as main earthwork