Protecting new asphalt overlay

Techniques can help in preventing cracks in underlying layers from penetrating to new surface layers - *Farzad Tooryani. For road repairs involving milling off worn asphalt surface layers before repaving, the use of crack sealing is a crucial task. This can help to prevent full reflection of existing cracks from underneath layers into the new wearing course. Once the milling work is complete, locating existing cracks is a crucial task for the site supervisor. Efficient routing equipment that is easy to hand
October 20, 2017 Read time: 3 mins
Once applied the sealant should be left for a week before paving is carried out

Techniques can help in preventing cracks in underlying layers from penetrating to new surface layers - *Farzad Tooryani

For road repairs involving milling off worn asphalt surface layers before repaving, the use of crack sealing is a crucial task. This can help to prevent full reflection of existing cracks from underneath layers into the new wearing course. Once the milling work is complete, locating existing cracks is a crucial task for the site supervisor. Efficient routing equipment that is easy to handle and fast in operation is used to prepare the cracks.

Where the crack width is less than 10mm, the user can rout the crack to a depth of 10mm. But if the width is greater than 10mm, the user should set the router to 20mm. The operator can guide the router on the cracks and follow them backward.

A key task after routing is to ensure that the area is clean of any debris as leaving any loose material or dust in place can result in a failure of the whole process. Using compressed air to blow out the debris is a useful technique, while a hot air lance (HAL) can also play a key role on sites where surface humidity levels are high. Any moisture left on the sides of the crack can result in early failures.

The user has to select a rubberised hot applied sealant that best suits the materials and weather conditions. This sealant can then be gravity fed using cones into the crack area, a simple and easy method to carry out. Indirect heating of the sealant in a special kettle before the material is applied is important for the best rest results. Heating the sealant ensures that it bonds properly with the sides of the crack, providing a longer lasting repair. For the most efficient application, the kettle should be equipped with an oil jacketed tank and simultaneous agitation.

Applying the sealant so that its top surface is around 2mm lower than the milled surface will minimise the need for raking with the new overlay. Once the sealant has been applied to the cracked areas, waiting for a week will then allow the material to settle properly. And before the new asphalt layer is laid, the milled surface should be cleaned effectively and also a suitable tack coat layer applied to ensure effective bonding. 

*Farzad Tooryani - owner & general manager at 8640 Sunway Sealing, the Middle East representative for Marathon Equipment

For more information on companies in this article

Related Content

  • Foaming option
    July 16, 2012
    Foamed bitumen is a versatile and cost-effective tool in recycling roads - Mike Woof reports Wirtgen hopes to capitalise on the growing demand for materials recycling and its range of solutions for this sector has expanded considerably in recent times. The firm has been taking advantage of further developments in foamed bitumen technology to offer an array of cost-effective road repair solutions. The range allows this material to be used in array of cold recycling applications and Wirtgen also offers labora
  • 'Blinding success' at Welsh quarry
    February 14, 2012
    Wales is renowned for many things but dry weather is not one of them. A combination of being close to the Atlantic and having lots of mountains means that it rains a lot and this is bad news when fine screening limestone using conventional steel wire mesh, which tends to clog and blind over in damp weather.
  • Maximising cone crusher efficiency
    September 30, 2013
    Ensuring efficient cone crusher operation can deliver major economies of scale for quarrying facilities There are a number of ways in which cone crusher throughput can be optimised. One of the key issues is in keeping the system choke fed during operation, as this maximises the effectiveness of rock-on-rock crushing, extends the wear life of manganese components and ensures a quality product shape. A lack of feed causes inconstant loading, which affects the long-term life of internal components.
  • Out of sight
    July 16, 2012
    With traffic volumes increasing around the world, many existing road links will need to be upgraded or replaced in coming years The need for new road tunnels is particularly intense in many dense urban areas, due to environmental requirements that mean new road links will have to be installed underground. However, improving existing road tunnel links is providing a very large part of the business for this specialised construction segment at present.