Protecting new asphalt overlay

Techniques can help in preventing cracks in underlying layers from penetrating to new surface layers - *Farzad Tooryani. For road repairs involving milling off worn asphalt surface layers before repaving, the use of crack sealing is a crucial task. This can help to prevent full reflection of existing cracks from underneath layers into the new wearing course. Once the milling work is complete, locating existing cracks is a crucial task for the site supervisor. Efficient routing equipment that is easy to hand
October 20, 2017 Read time: 3 mins
Once applied the sealant should be left for a week before paving is carried out

Techniques can help in preventing cracks in underlying layers from penetrating to new surface layers - *Farzad Tooryani

For road repairs involving milling off worn asphalt surface layers before repaving, the use of crack sealing is a crucial task. This can help to prevent full reflection of existing cracks from underneath layers into the new wearing course. Once the milling work is complete, locating existing cracks is a crucial task for the site supervisor. Efficient routing equipment that is easy to handle and fast in operation is used to prepare the cracks.

Where the crack width is less than 10mm, the user can rout the crack to a depth of 10mm. But if the width is greater than 10mm, the user should set the router to 20mm. The operator can guide the router on the cracks and follow them backward.

A key task after routing is to ensure that the area is clean of any debris as leaving any loose material or dust in place can result in a failure of the whole process. Using compressed air to blow out the debris is a useful technique, while a hot air lance (HAL) can also play a key role on sites where surface humidity levels are high. Any moisture left on the sides of the crack can result in early failures.

The user has to select a rubberised hot applied sealant that best suits the materials and weather conditions. This sealant can then be gravity fed using cones into the crack area, a simple and easy method to carry out. Indirect heating of the sealant in a special kettle before the material is applied is important for the best rest results. Heating the sealant ensures that it bonds properly with the sides of the crack, providing a longer lasting repair. For the most efficient application, the kettle should be equipped with an oil jacketed tank and simultaneous agitation.

Applying the sealant so that its top surface is around 2mm lower than the milled surface will minimise the need for raking with the new overlay. Once the sealant has been applied to the cracked areas, waiting for a week will then allow the material to settle properly. And before the new asphalt layer is laid, the milled surface should be cleaned effectively and also a suitable tack coat layer applied to ensure effective bonding. 

*Farzad Tooryani - owner & general manager at 8640 Sunway Sealing, the Middle East representative for Marathon Equipment

For more information on companies in this article

Related Content

  • Brazilian contractor uses novel methods for high quality road
    January 5, 2015
    Cold-in place recycling method provides fast road rebuild in Brazil In Brazil a road contractor has carried out a high quality road rebuilding job, using novel techniques. Contractor Brown Brown is located in Santa Teresinha in the state of Bahia and recently carried out a two-week job for the company to rehabilitate sections of highway BR-381. The highway is an important route in Brazil and runs from Sao Paulo to Belo Horizonte. Highway BR-381 or Rodovia Fernão Dias, as it is called, stretches some 576km
  • Kuwait’s key causeway contract under construction
    July 4, 2016
    A new causeway, crossing the Bay of Kuwait, is under construction and providing a major engineering challenge - Mike Woof reports. The new Sheikh Jaber Al-Ahmad Al-Sabah Causeway Project being built across the Bay of Kuwait is a massive engineering project that is costing around US$3 billion in all. This highly complex project involves the design, build, completion and maintenance of the causeway, which spans Kuwait Bay between Kuwait City and the Subiyah area. The 36km Sheikh Jaber Al-Ahmad Al-Sabah Cau
  • Ensuring screening efficiency can cut costs
    September 30, 2013
    Major Wire Industries, a leading manufacturer of screen media, has determined a numbers of methods to tackle common screening problems Screen media inefficiencies can reduce product quality, production and profit as much as a poorly performing screen box. Screen media modifications cost less than screen box upgrades and can provide major benefits for little outlay. If material is coming off the end of the deck, instead of passing through the screen cloth there are several possible problems. It could be that
  • BituChem’s AirPatch pothole repair system is way out in front
    November 20, 2017
    BituChem, the manufacturer of AirPatch, says that the product formulation can be altered so local aggregate is chemically compatible, making the pothole patch more durable. AirPatch is a sprayed application that provides an excellent break and pothole repair solution. It repairs potholes and other surface deformations by spraying the surface with aggregate. BituChem says that AirPatch is also a superb adhesion binder.