Efficient milling and re-paving on historic Florence streets

Maintenance of roads in historic districts is a challenge for communities around the world. The sanctity of the surroundings limits the amount of re-engineering and widening that can be considered. Improvement options typically are limited to repairs. Yet repairs also have an impact. The historic areas usually attract tourists and their crucial economic contributions. If the street repairs create too much of an inconvenience, tourists are likely to avoid the area and a negative economic impact and a loss of
February 1, 2013 Read time: 5 mins
Removing the existing, damaged surface was the first step in the project
Maintenance of roads in historic districts is a challenge for communities around the world. The sanctity of the surroundings limits the amount of re-engineering and widening that can be considered. Improvement options typically are limited to repairs.

Yet repairs also have an impact. The historic areas usually attract tourists and their crucial economic contributions. If the street repairs create too much of an inconvenience, tourists are likely to avoid the area and a negative economic impact and a loss of goodwill with area merchants can easily result. But deteriorating streets that are not repaired also can impact travel, and reflect poorly on the community.

Outside visitors and merchants aren’t the only people of concern. The local residents who use the streets for their own purposes are also likely to be vocal over the condition and repair of roads.

Florence, Italy, found itself in a difficult balancing act. Streets in its District 5 were deteriorating rapidly. Yet the city couldn’t make comprehensive changes given the footprint of the roads in relation to the historical surroundings. Still, something clearly needed to be done.

Taking action

The city of Florence came up with an innovative plan. It gave Italian paving contractor 7131 AVR SpA complete control of street repairs in District 5. The initial contract ran for four months, and was then extended for two more months.

AVR monitored the roads in a variety of ways. Its own staff spotted trouble spots. It also created a 24-hour call centre that could be accessed by police, city workers and AVR staff who observed potholes and other obstructions. The reports of road problems were categorised as “emergency,” when action was required within 45 minutes, or “non-emergency,” which allowed crews to respond within three days.
AVR also conducted its own safety analysis of the road network to identify infrastructure dangers, and prioritised the work associated with its findings.

Viale Corsica work

One District 5 street, Viale Corsica, quickly became a priority project. The extent of the deterioration meant the road needed to be repaired, not simply patched.

The most urgent repairs were needed in the bus lane. The lane is crucial to travel for thousands in the district. The repair work would have to be completed quickly.

The bus lane is adjacent to other traffic lanes that had to remain open, meaning tight, maneuverable equipment was required. Yet the demands of the job meant productivity couldn’t be sacrificed.

AVR turned to the Cat® PM200 Cold Planer to remove the existing, damaged surface; the Cat AP600D Asphalt Paver to place the new surface; and a Cat CD54 Tandem Vibratory Roller to ensure the new mat had the density required to support the projected loads for a long time.

“The intervention was not particularly difficult from a technical point of view, but posed some problems relevant to the need of working on the congested road at peak times, having to leave one lane open,” said Lorenzo Porciani, AVR Manager. “We milled and rebuilt 4cm of mat, about 350m long and 12m wide.”

AVR SpA

• Work includes road building and maintenance.
• Handles commercial building construction.
• Sustainability efforts include reuse of asphalt during reclaiming process; also handles chemical and physical reclamation of polluted sites.
• Clients include a number of Italian governmental agencies.
• Operations in Lazio, Tuscany and Calabria, Italy; subsidiaries in Lombardy and Puglia.
AVR watched the Viale Corsica project closely, as did City of Florence officials. Work on that street was used as barometer of how the equipment would handle necessary repairs on other tight streets. The project was successful, and now medium to large interventions—those above 100m² of extension—will use five Cat machines: The PM 200, AP600D, CB34XW, CB434D and CD54.

“The machines were productive and able to function well within the limitations of the bus lane,” Porciani said.

Choosing a machine

AVR chose Caterpillar because of the machines’ productivity and the customer service support through Italian Dealer, 7132 CGT. A recommendation from another paving contractor also played a key role.

“We opted for a Caterpillar fleet, for the undoubted excellent features of the machines that were also praised by another important company with whom we worked in the past,” said Porciani. “We also appreciated the guarantees offered by a Cat Dealer such as CGT. From technical assistance to rental, if needed, we know we can count on them, with the great advantage of having a single point of contact for all needs.”

The final results

The machines performed well on the Viale Corsica jobsite. “Thanks to the high productivity of the Cat PM200, to the excellent qualities of paving and compaction of the AP600D and CD54, we finished in a day, and replaced the road signs the following day,” Porciani said.

The Cat machines continue to handle the more extensive District 5 repairs, while AVR also pursues other improvements such as pothole patching. The scope of the work has proven to be a success for both AVR and the City of Florence. In six months more than 5,000 potholes were filled in District 5, including 143 emergency patching projects. In addition, more than 84 milling and repaving operations occurred on 20 different district streets.

“For the toughest jobs, AVR relies on 4018 Caterpillar Paving machines and the Italian dealer CGT for service,” Porciani said.A story by Caterpillar Paving %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Click here www.paving-news.com/register/ false http://www.paving-news.com/register/ false false%> to register for your personal copy of Paving News

For more information on companies in this article

Related Content

  • Brazil roads repaired with Wirtgen equipment
    November 6, 2018
    A large milling machine from Wirtgen has been used to help repair busy roads in the vicinity of São Paulo in Brazil. The roads provide important transport connections as they link São Paulo with Santos, Brazil’s largest port. The Anchieta-Imigrantes highway system provides the main link between the metropolitan region of São Paulo and the port of Santos, the busiest port in Latin America. Construction of the Anchieta highway began in 1947, with Imigrantes following at the start of the 1970s. Today the Anch
  • Race track rebuild in Italy
    May 15, 2019
    A motor racing circuit in Italy has benefited from a new asphalt surface, with the paving work carried out by machines from Sumitomo.
  • The European Union Road Federation (ERF) calls for EU Member States to prioritise road maintenance
    June 26, 2014
    The European Union Road Federation (ERF) has put out an “urgent” call for “EU Member States to prioritise road maintenance” as neglected surfaces continue to deteriorate and the potholes grow larger and larger. ERF wants the EU to “put alternative financing mechanisms into place” as soon as possible, to tackle what it sees as a growing road safety crisis across the region. At its first ERF biennial Symposium on Road Infrastructure Challenges in June, more than 100 stakeholders heard the ERF demand the “ope
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of