Efficient milling and re-paving on historic Florence streets

Maintenance of roads in historic districts is a challenge for communities around the world. The sanctity of the surroundings limits the amount of re-engineering and widening that can be considered. Improvement options typically are limited to repairs. Yet repairs also have an impact. The historic areas usually attract tourists and their crucial economic contributions. If the street repairs create too much of an inconvenience, tourists are likely to avoid the area and a negative economic impact and a loss of
February 1, 2013 Read time: 5 mins
Removing the existing, damaged surface was the first step in the project
Maintenance of roads in historic districts is a challenge for communities around the world. The sanctity of the surroundings limits the amount of re-engineering and widening that can be considered. Improvement options typically are limited to repairs.

Yet repairs also have an impact. The historic areas usually attract tourists and their crucial economic contributions. If the street repairs create too much of an inconvenience, tourists are likely to avoid the area and a negative economic impact and a loss of goodwill with area merchants can easily result. But deteriorating streets that are not repaired also can impact travel, and reflect poorly on the community.

Outside visitors and merchants aren’t the only people of concern. The local residents who use the streets for their own purposes are also likely to be vocal over the condition and repair of roads.

Florence, Italy, found itself in a difficult balancing act. Streets in its District 5 were deteriorating rapidly. Yet the city couldn’t make comprehensive changes given the footprint of the roads in relation to the historical surroundings. Still, something clearly needed to be done.

Taking action

The city of Florence came up with an innovative plan. It gave Italian paving contractor 7131 AVR SpA complete control of street repairs in District 5. The initial contract ran for four months, and was then extended for two more months.

AVR monitored the roads in a variety of ways. Its own staff spotted trouble spots. It also created a 24-hour call centre that could be accessed by police, city workers and AVR staff who observed potholes and other obstructions. The reports of road problems were categorised as “emergency,” when action was required within 45 minutes, or “non-emergency,” which allowed crews to respond within three days.
AVR also conducted its own safety analysis of the road network to identify infrastructure dangers, and prioritised the work associated with its findings.

Viale Corsica work

One District 5 street, Viale Corsica, quickly became a priority project. The extent of the deterioration meant the road needed to be repaired, not simply patched.

The most urgent repairs were needed in the bus lane. The lane is crucial to travel for thousands in the district. The repair work would have to be completed quickly.

The bus lane is adjacent to other traffic lanes that had to remain open, meaning tight, maneuverable equipment was required. Yet the demands of the job meant productivity couldn’t be sacrificed.

AVR turned to the Cat® PM200 Cold Planer to remove the existing, damaged surface; the Cat AP600D Asphalt Paver to place the new surface; and a Cat CD54 Tandem Vibratory Roller to ensure the new mat had the density required to support the projected loads for a long time.

“The intervention was not particularly difficult from a technical point of view, but posed some problems relevant to the need of working on the congested road at peak times, having to leave one lane open,” said Lorenzo Porciani, AVR Manager. “We milled and rebuilt 4cm of mat, about 350m long and 12m wide.”

AVR SpA

• Work includes road building and maintenance.
• Handles commercial building construction.
• Sustainability efforts include reuse of asphalt during reclaiming process; also handles chemical and physical reclamation of polluted sites.
• Clients include a number of Italian governmental agencies.
• Operations in Lazio, Tuscany and Calabria, Italy; subsidiaries in Lombardy and Puglia.
AVR watched the Viale Corsica project closely, as did City of Florence officials. Work on that street was used as barometer of how the equipment would handle necessary repairs on other tight streets. The project was successful, and now medium to large interventions—those above 100m² of extension—will use five Cat machines: The PM 200, AP600D, CB34XW, CB434D and CD54.

“The machines were productive and able to function well within the limitations of the bus lane,” Porciani said.

Choosing a machine

AVR chose Caterpillar because of the machines’ productivity and the customer service support through Italian Dealer, 7132 CGT. A recommendation from another paving contractor also played a key role.

“We opted for a Caterpillar fleet, for the undoubted excellent features of the machines that were also praised by another important company with whom we worked in the past,” said Porciani. “We also appreciated the guarantees offered by a Cat Dealer such as CGT. From technical assistance to rental, if needed, we know we can count on them, with the great advantage of having a single point of contact for all needs.”

The final results

The machines performed well on the Viale Corsica jobsite. “Thanks to the high productivity of the Cat PM200, to the excellent qualities of paving and compaction of the AP600D and CD54, we finished in a day, and replaced the road signs the following day,” Porciani said.

The Cat machines continue to handle the more extensive District 5 repairs, while AVR also pursues other improvements such as pothole patching. The scope of the work has proven to be a success for both AVR and the City of Florence. In six months more than 5,000 potholes were filled in District 5, including 143 emergency patching projects. In addition, more than 84 milling and repaving operations occurred on 20 different district streets.

“For the toughest jobs, AVR relies on 4018 Caterpillar Paving machines and the Italian dealer CGT for service,” Porciani said.A story by Caterpillar Paving %$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Click here www.paving-news.com/register/ false http://www.paving-news.com/register/ false false%> to register for your personal copy of Paving News

For more information on companies in this article

Related Content

  • Qatar’s new highway requires huge logistics operation
    October 26, 2016
    In the Middle East nation Qatar, a large-scale highway project is underway that will make significant improvements for vehicle capacity and cut journey times for drivers. The new route will also improve transport connections between Qatar’s ports and neighbouring Saudi Arabia. At the same time, the new highway will carry much of the heavy vehicle traffic travelling between the two countries.
  • French fine milling achieved
    January 10, 2025
    Contractor 2AGE-MCS achieved precision and speed in milling the Route Centre-Europe Atlantique in France with the use of 3D technology
  • Active travel can drive urban economic growth and save health funds
    November 7, 2012
    Experts in health, city planning, environment and transport from Europe and the United States, including several local authorities, stressed how active travel can drive urban economic growth and save public health funds during a recent prestigious workshop event in Brussels, Belgium. Integrating health aspects in transportation planning was the focus of The Polis Environment & Health working group meeting at the European Economic and Social committee on 30th October. The event gathered experts from organisa
  • Pilosio Building Peace Awards event attracts high profile speakers
    November 10, 2015
    Actress Sharon Stone challenged guests at the fifth annual awards in Milan to “build me a school”; they accepted. World Highways was there. What does it take to galvanise people into action to help people in need, especially refugees during a time of conflict – as in Syria now? For some it has been the recent media stories – and distressing images – of the child Aylan Kurdi, a three-year old Syrian refugee whose lifeless body lay face down on a beach in Turkey.