Asphalt paving trial for mat quality using MTVs

An asphalt paving trial at Rome Airport tested mat quality with and without the use of MTVs Rome’s airport Fiumicino or the Leonardo da Vinci Airport of Rome is one of Europe’s busiest airports and lies 25.6km southwest of the city, a 30-minute train ride away.
December 8, 2015 Read time: 4 mins
Local contractor Pavimental used milling machines to remove the old surface of Rome Airport’s runway before bringing in a paving train for resurfacing
RSS

An asphalt paving trial at Rome Airport tested mat quality with and without the use of MTVs

Rome’s airport Fiumicino or the Leonardo da Vinci Airport of Rome is one of Europe’s busiest airports and lies 25.6km southwest of the city, a 30-minute train ride away. Handling just over 38.5 million passengers in 2014, the airport’s three runways carry heavy traffic, so much so that the runway 16L/34R recently required resurfacing. The 3,902m long by 60m wide runway had to be milled and repaved, with local contractor Pavimental winning the contract. The company is considered the leader in asphalt production in Italy.

Before full paving production began on the project, Pavimental wanted to test whether a 1252 Roadtec SB-2500e Shuttle Buggy material transfer vehicle (MTV) could reduce thermal segregation in the hot-mix asphalt (HMA) and ensure a higher-quality finished mat.

The Fiumicino 16L/34R runway project was less than five minutes away from the asphalt plant so the contractor was initially doubtful that MTVs could offer benefits.

The contractor used its 1194 Vögele Super 2100-3i tracked paver for the work, a heavy-duty machine with a maximum laydown rate of 1,100tonnes/hour and a maximum pave width of 13m.

For the three tests conducted, Pavimental had 1228 MOBA as an independent quality controller. MOBA used its PAVE-IR Scan to detect the thermal segregation on the recent paved test layers. The PAVE-IR Scan allows recording of asphalt temperature while paving. It depict a temperature profile and highlights the differences that lead to thermal segregation of the material and identifies areas where premature wear and tear of the road may occur.

Pavimental used the PAVE-IR Scan system to show the overall quality achieved by each paving method. One was paving with the help of the Roadtec SB-2500e/ex Shuttle Buggy MTV. Another was with HMA trucked from the production plant and loaded into the paver.

The determining factor in the research test was to measure the level of thermal segregation occurring in the asphalt mat behind each paving method. In the past, extensive testing resulted in Stroup-Gardiner and Brown establishing in 2000 a classification of thermal segregation and its related consequences. In the classification system, when temperature differences are below 10ºC segregation is considered nonexistent, between 10ºC and 16ºC it is low, between 17ºC and 21ºC medium and it is considered high when over 21ºC.

The higher the measured temperature, the more likely the paved surface will experience fatigue and be less durable. What all the tests point out is that temperature deviations will make pavement less durable and will increase maintenance costs.

For the Rome international airport test, a lift was laid by each method. The testing occurred over a six-day period with test mats laid by each method.

MOBA used infrared scanning to examine the level of thermal segregation. The results concluded that the finished pavement quality from each paving method show a temperature change of <8ºC when using the Roadtec Shuttle Buggy and temperatures varied from between 20ºC and 25ºC when trucked HMA was loaded directly into the paver.

The collected data shows that when the Roadtec Shuttle Buggy is used the maximum thermal segregation detected is 8ºC, so the results indicate NULL segregation, while when the PowerFeeder or direct truck-to-paver methods are used the temperature differentials can be more than 20ºC at any given time. The trucked-in methods will have durability that is expected to be about half of what can be achieved through the Roadtec Shuttle Buggy, which remixes the HMA and provides continuous paving.

Pavimental found the results useful. The initial thinking was that with the HMA production source so close to the jobsite, there would be no need for a material transfer vehicle. However the results of the thermal segregation tests suggest otherwise.

RSS

For more information on companies in this article

Related Content

  • MOBA system measures temperatures, improves quality
    April 22, 2015
    MOBA’s paving quality control technology just became more accurate and easier for crews to utilise. The MOBA Pave-IR temperature system now utilises a sensor, more accurate than the previous laser beam technology. The sensor also provides easy crew access. The use of the sensor, compared with the previous beaming system, is a significant step forward, said Marcus Watermann, Product Manager for Paving Quality Systems at MOBA Mobile Automation. “The improved access is important because the systems is a key to
  • Asphalt plant assists at airport project
    December 19, 2017
    An asphalt plant from ADM has helped in the reconstruction of the runway at South Caicos Airport. Herzog Caribbean recently took delivery of its new asphalt plant to supply material for the runway overhaul on South Caicos Island. The plant, an ADM EX120, delivered 23,000tonnes of material for the project without any downtime, allowing for an April 2017 completion. A division of Missouri-based Herzog Contracting, Herzog Caribbean operates out of Providenciales, the capital city of Turks & Caicos, British We
  • Concrete runway paving in the US
    December 15, 2017
    A new Wirtgen SP 94i slipform paver has helped deliver the successful reconstruction of a runway in the US state of Missouri. With more than 30,000 take-offs and landings a year, Jefferson City Memorial Airport (JEF) is one of the most heavily frequented airports in Missouri. Thousands of visitors travel through it every day on their way to the government and congress offices in the state capital on the Missouri River. At the end of April 2016, work commenced on the reconstruction of a runway approximately
  • This runway builder perfected paving and landed remarkable results
    August 31, 2023
    This busy airport needed a complete runway renovation without disrupting daily scheduled take-offs and landings. Each workday, construction could start no sooner than 11pm and couldn’t end a minute past 6am. Without state-of-the-art technology from Trimble—including 3D machine guidance—and expert training from SITECH, this complex and high-precision project would've never got off the ground.