Serbia upgrading infrastructure

Serbia has managed to reduce the cost of building the Corridor 10 highway by €80 million. These funds will instead be used to pay for upgrades and improvements needed for the second section of the highway project, close to Neradovci.
March 16, 2012 Read time: 2 mins
Serbia has managed to reduce the cost of building the Corridor 10 highway by €80 million. These funds will instead be used to pay for upgrades and improvements needed for the second section of the highway project, close to Neradovci. So far some 180km of the Corridor 10 highway has been built over a 40 month time frame. A further 150km of the highway has still to be built. Work on the Corridor 10 motorway is also being financed by the 1166 European Bank for Reconstruction and Development and the state budget. When Corridor 10 is complete it will provide a valuable transport link for Serbia to its neighbours and also for the region.

Work on the 40km Belgrade ringroad section of the Corridor 10 highway is due to be completed by May 2012, six months before the deadline. The ringroad runs from Batajnica to Bubanj Potok and work is being carried out by the Austrian company 945 Strabag.

The construction work includes building two viaducts, each 1.5km long.

In July 2009, the 2332 World Bank (WB) approved a total of €299 million for construction of the Corridor 10 highway. The WB will allocate €100 million for road maintenance, rehabilitation and road safety improvements in Serbia. Funding will be approved as part of the WB's four year partnership strategy between 2012 and 2015. During the mentioned period, the WB is planning to secure between €462.5-617 million for financing in Serbia. In addition, the Serbian Government has awarded construction of two 25km sections of the Belgrade-Cacak highway project to contractors from Azerbaijan and Russia.

The Obrenovac-Ub to Lajkovac-Ljig section is being handled by a Russian firm, while the Ljig to Cacak stretch is being offered to a firm from Azerbaijan. Some 180km of the highway has been completed.

The tender process for a further 150km of the highway is still underway at present. The Belgrade-Cacak motorway project is estimated at €500 million.

Austrian construction company 3976 PORR is planning to participate in new tenders for construction of the Corridor 10 motorway and the environmental protection projects. The company successfully completed construction of the Ada Ciganlija Bridge in Belgrade, worth €120 million, and construction of a new transportation node worth €70 million. However, Porr will continue with the arbitration process to claim €70 million for cancellation of the concession deal, for the Horgos-Pozega highway.

For more information on companies in this article

Related Content

  • New highway connections planned for Serbia
    September 6, 2012
    The authorities in Serbia are pushing ahead with plans for the Corridor 10 and Corridor 11 highways. Serbia's national state owned highway company, Koridori Srbije, has awarded the contract for advisory services for the €1.9 billion Corridor 10 project to French company Egis International. Under the terms of the deal Egis will provide support for construction of 83.4km of the E-80 highway between the City of Nis and the Bulgarian border at Dimitrovgrad.
  • Russia to commission new Moscow-St Petersburg highway by 2020
    June 20, 2017
    Final delivery of the final stretch for Russia’s key highway project looks set to be delayed – Eugene Gerden writes. I now looks as if Russia’s most ambitious project in the field of road building in recent years, the building of a new high-speed road link between Moscow and St Petersburg, the country’s largest cities, will not be complete in time. The project was set up by the Russian government and several private investors. According to initial state plans, building of the new road should have been compl
  • Congestion and safety concerns over Serbia’s roads
    February 23, 2012
    With traffic flows on the increase, Serbia needs to improve its road network and safety record, reports Gordon Feller. Serbia's road network needs to upgrade its road system against the backdrop of increased traffic flows. Serbia is crossed by segments of the important Trans European network (TEN). Corridor X with its branches Xb (Belgrade-Budapest) Xc (Nis-Sofia), and Xd (Nis-Presevo), represent the most important transit routes in the Republic, connecting Austria/Hungary, Slovenia/Croatia, and Bulgaria/Ma
  • Delay for major Serbian highway project
    August 19, 2016
    Construction work on Serbia’s Ljig-Preljina highway, the Corridor 11 Project, is being delayed. The delay has been caused by complications involving the construction of the tunnel and bridge sections. The construction work is being carried out by the Azerbaijan contractor Azvirt, with local firms carrying out sub-contracting projects. The new route is expected to open around 40 days later than originally expected as a result. Meanwhile the improving political relations between Serbia and its neighbour Ko