A major road in Norfolk has been improved following the installation of Tarmac’s largest ever supply of a specialist asphalt solution. This material grade has been designed to maintain roads where the underlying concrete has deteriorated
November 10, 2021 Read time: 2 mins
A special asphalt grade has been used to overlay deteriorating concrete on the A11 in the UK

The lean concrete base of an 8km section on both carriageways of the A11 near Thetford was identified as in need of repair. Tarmac was tasked with finding a long-lasting surface that would cut life cycle maintenance costs.

Working in partnership with National Highways and project consultants Atkins and following a whole-life cost analysis, Tarmac suggested the use of its fully recyclable ULTILAYER SAMI asphalt, a high-performance stress absorbing membrane interlayer. The team laid 80,000tonnes of material, including 7,000tonnes of ULTILAYER SAMI, the most Tarmac has ever supplied to a single project. In addition to being fully recyclable, this special asphalt is expected to increase the life of the pavement, resulting in lower maintenance requirements.

Phil Greenin, contracting framework delivery manager at Tarmac, said: “ULTILAYER SAMI is a proven technology that has been developed to tackle deteriorating concrete roads. Its previous applications on the strategic network, including on the M25, have demonstrated that its greater whole-life performance can extend pavement life, deliver longer resurfacing intervals and lower maintenance requirements.

Conventional asphalt grades used to overlay concrete often suffer from reflective cracking caused by thermal expansion in the underlying concrete and the effects of traffic loading. This leads to water ingress and failure that requires remedial work.

Designed to be laid onto concrete, the material is a finely-graded asphalt containing a heavily polymer modified binder (PMB), which provides a durable buffer to accommodate movement and prevent cracks appearing in the asphalt layers above. This was overlaid with a polymer modified binder course and surface course material to further increase the crack resistance of the carriageway.   

In addition to the new surface’s improved sustainability credentials, the Tarmac project team is ensuring that 100% of the old surface material will be recycled and is implementing a ‘carbon calculator’ to accurately identify where other emissions savings have been achieved.

For more information on companies in this article

Related Content

  • Australian firm uses recycled feed material for asphalt
    August 14, 2015
    Innovations in asphalt plant technology will help boost the use of recycled asphalt. Mike Woof writes. An Ammann asphalt plant located in Australia has been successful in using a high percentage of recycled feed materials. The Australian producer Downer recently created and laid an asphalt mix consisting of 99% recycled materials, including feed from somewhat unusual sources. The feed included toner from printer cartridges, tyres and glass and this is thought to be the first time a mix has been produced usi
  • Bonjour bio-based binders
    April 5, 2023
    How can Shell speed the whole road construction sector on its way to decarbonisation? Professor John Read and Richard Taylor have a few ideas.
  • Resilient roads: sector cooperation is the key
    March 11, 2021
    Now is the time for national road agencies and the private sector to cooperate on building more climate resilient roads, urges Dr Erik Denneman*.
  • Eurovia races against the clock for London’s Race of Champions
    June 17, 2016
    Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium. The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award. The circuit was co