Volz makes headway in Hesse

A road contractor in Germany is making use of a sophisticated logistics tool to run its operations more efficiently. The contractor, Wilhelm Schütz, is a medium-sized company with a long history in road construction and civil engineering. Based in Hesse, the firm has its own mixing plant to supply material to its road construction crews.
November 22, 2018 Read time: 3 mins
German road contractor Wilhelm Schütz was already familiar with BPO tools from Volz Consulting

A road contractor in Germany is making use of a sophisticated logistics tool to run its operations more efficiently. The contractor, Wilhelm Schütz, is a medium-sized company with a long history in road construction and civil engineering. Based in Hesse, the firm has its own mixing plant to supply material to its road construction crews.

The firm was looking to optimise its operations in a bid to boost efficiency and reduce waste, using the latest tools intended for the digitisation of existing processes and processes. The company’s weighing system had been in use for 15 years and was a key link for improving overall performance.

The construction company was already familiar with technology solutions from 8820 Volz Consulting. As a result, Wilhelm Schütz, opted to introduce the software system for raw material production as this would allow the firm to use a complete system from one manufacturer.

The BPO Baustoff package can be used for the value chain, from operation and resource management to merchandise management, such as purchasing, sales, invoicing, freight accounting, production data collection, production and logistics. Users of the package can employ it for material production as well as road milling and paving applications.

Due to real-time networking, data such as delivery notes, invoices, material orders and offers can be exchanged. Deliveries of minerals from an asphalt mixing plant can be monitored automatically and need only to be confirmed. Raw material orders can be transmitted electronically, reducing order costs.

For Wilhelm Schütz, direct networking with its BPO Asphalt package meant that the firm could automatically exchange delivery note data as well as schedule data automatically between both systems, but without manual input. This could offer time saving for internal processes. This has now provided a better flow of information, with fewer searches and queries while at the same time providing leaner structures and lower administrative costs.

The weighing supervisor is presented with all planned material deliveries for the respective day. Due to the search and copy options, documents can be created efficiently and incorrect entries can be avoided.

As delivery notes are electronically signed on a signature pad and at the same time stored as PDF in an archive, the weighing supervisor can focus on important tasks at the balance. It is also possible to assign the articles to the applicable Construction Products Regulation - all prescribed contents are clearly displayed on the delivery note.

Price variants can be deposited in the software and any assignments are now automatic. Previously, prices had to be entered manually, rechecked and corrected if necessary. The connection to financial accounting programs has also been simplified.

"We can handle the entire business process from quoting, order management, weighing, mass control to billing in one program,” said Steffen Richter, operations manager for the mixing plant.

“For us, this means a better overview and much time savings. The changeover process and the training of our employees took place in a short time and without any problems. By integrating BPO Asphalt, the construction progress can be tracked in real time and the coordination of material flows is facilitated. The site manager in the office can also follow the construction progress online," he said.

For more information on companies in this article

Related Content

  • Kistler Lineas strip sensors receive OIML certification
    September 15, 2015
    Kistler has announced that its Weigh-In-Motion (WIM) system consisting of Lineas quartz WIM sensors and the Kistler WIM Data Logger has been OIML R-134 certified. Kistler said its WIM system precisely measures axle loads and vehicle weights from low to high speed. It is now, with the OIML certificate (International Organisation of Legal Meteorology) also certified for legal applications from low to medium speed (3-65 kph) with accuracy class 5 and class 10. This enables the automatic collection of wei
  • Simex unveils GEN II of ART 1000 asphalt regeneration tech
    March 6, 2025

    Simex has released the new GEN II version of its ART 1000 patented technology for in-situ regeneration of deteriorated asphalt.

    Simex ART technology focuses on surface-level interventions for the functional recovery of road deterioration. It does not require the removal of milled material or the addition of virgin bituminous mix, instead utilising only the existing on-site material. Most importantly, it avoids the complete interruption of vehicular traffic, ensuring the road is immediately passable after restoration.

  • Concrete paving job for Wirtgen machines in Nigeria
    May 14, 2018
    Concrete paving equipment from Wirtgen has been used to slipform a concrete road surface in south-west Nigeria Anew concrete roadway connects the towns of Itori und Ibese in Nigeria’s Ogun State. The construction work has been carried out by AG-Dangote Construction Company and made use of the sophisticated technology offered by Wirtgen’s SP 500 slipform paver. For this project, the contractor, a joint venture between the Brazilian company Andrade Gutierrez Company and the Dangote Group from Nigeria, rel
  • Multiple asphalt plants supply major highway construction
    July 12, 2012
    One company has produced eight asphalt plants for a major project, and others are introducing new models as Patrick Smith reports Algeria's US$11.2 billion East-West Highway development, the world's largest current highway construction project, forms part of the larger Trans-Maghreb Motorway project, and is scheduled for completion in 2010. It will run for 1,216km, ensuring the link between Annaba in the north-east and Tlemcen in the north-west, passing directly through 24 provinces and linking Algeria to T