Salzburg runway rebuild completed

Salzburg Airport in Austria is now benefiting from a 2.75km runway, following major redevelopment work at the facility The new 2.75km runway was rebuilt following a total shutdown of flights at the airport for five weeks. The rebuilding work was assisted by the use of a compact crusher supplied by Linz-based Rubble Master. This unit was used to crush 8,500tonnes of material on-site at Salzburg Airport, with the material being immediately reused. "This job was a challenge due to its tight time schedule,"
September 6, 2019 Read time: 2 mins
Salzburg Airport now has a new runway, with a compact crusher from RUBBLE MASTER having been used to recycle materials on-site - image courtesy of RUBBLE MASTER
Salzburg Airport in Austria is now benefiting from a 2.75km runway, following major redevelopment work at the facility


The new 2.75km runway was rebuilt following a total shutdown of flights at the airport for five weeks. The rebuilding work was assisted by the use of a compact crusher supplied by Linz-based 747 Rubble Master. This unit was used to crush 8,500tonnes of material on-site at Salzburg Airport, with the material being immediately reused.

"This job was a challenge due to its tight time schedule," said Klaus Weickl, managing director of Weickl Erdbau. "We only had four weeks to complete all the work."

The rented, compact RM 100GO! crusher was able to work directly on-site at Salzburg Airport and in just under a week was able to crush all the material from the 2.75km-long runway into a recyclable final aggregate. This value aggregate was used for the substructure of the new runway. Weickl said that the sustainable use of resources made the project more effective and efficient, reducing transport needs, materials costs and lowering the overall environmental impact of a project. The firm has used crushing equipment from Rubble Master for on-site crushing on previous contracts, such as a section of the A99 Autobahn in Munich where it used an RM 120GO! model.

For more information on companies in this article

Related Content

  • Runway rebuild for key Bulgarian airport
    August 21, 2013
    Varna Airport in north-east Bulgaria provides an important international link for the country, with a runway rebuild helping improve capacity. The airport is of particular importance for Bulgaria’s tourist trade as it provides a major connection for visitors to the Black Sea coast. And the reconstruction work at Varna Airport’s only runway will ensure the facility is able to handle the area’s increasing visitor numbers. The project had to be carried out quickly and efficiently to prevent delays to f
  • Rebuilding the busy Frankfurt Airport in Germany
    September 12, 2017
    Handling up to 450 take-offs/day, Runway West is Frankfurt Airport’s busiest runway. Over 50% of the aircraft taking off from the airport uses Runway West, and a point worth noting is that this German airport is one of the busiest in Europe. In 2016, Frankfurt Airport handled nearly 61 million passengers, surpassed by Schiphol in Amsterdam and Charles de Gaulle in Paris, Europe’s third and second busiest airports respectively. Meanwhile London’s Heathrow remained Europe’s busiest airport
  • Rebuilding the busy Frankfurt Airport in Germany
    September 12, 2017
    Handling up to 450 take-offs/day, Runway West is Frankfurt Airport’s busiest runway. Over 50% of the aircraft taking off from the airport uses Runway West, and a point worth noting is that this German airport is one of the busiest in Europe. In 2016, Frankfurt Airport handled nearly 61 million passengers, surpassed by Schiphol in Amsterdam and Charles de Gaulle in Paris, Europe’s third and second busiest airports respectively. Meanwhile London’s Heathrow remained Europe’s busiest airport
  • Aggregates advantages with new equipment
    November 4, 2019
    New equipment being introduced for the crushing and screening sector offers benefits for aggregate production – Mike Woof writes