High speed highway repair

A high speed highway rehabilitation has seen the repaving of a 1.5km stretch of road in just two night shifts. A Vögele SUPER 1800-2 paver fitted with one of the firm's SprayJet modules helped boost productivity and cut operating costs for Dutch contractor MNO Vervat.
February 29, 2012 Read time: 3 mins
Compaction equipment from Hamm was used to complete the surface work carried out by the Vögele paver
A high speed highway rehabilitation has seen the repaving of a 1.5km stretch of road in just two night shifts. A 1194 Vögele SUPER 1800-2 paver fitted with one of the firm's SprayJet modules helped boost productivity and cut operating costs for Dutch contractor 1642 MNO Vervat. The contract was the first time that the paving team had used its new Vögele SUPER 1800-2 with SprayJet Module in the Netherlands and has been used on a highway upgrade on the A6 near Amsterdam. The team quickly learned the operation of the machine and as surface upgrade was to be carried out by a thin overlay paved on spray seal, hot on hot, the paver applied emulsion and laid asphalt in one pass.

The A6 stretches from Amsterdam to Heerenveen in the north of the country and the surface course needed replacing for a 1.5km section to the north of Amsterdam. The first step involved milling off 20mm of the old surface between the Almeerderzand and Almere-Stad-West junctions using a 2395 Wirtgen planer fitted with a fine milling drum, before the new surfacing was to be paved.

This approach was used as the contractor, MNO Vervat, had convinced the authorities that using the Microville material for a thin overlay, with spray seal, hot on hot, was an effective solution. M Zwaan of the Dutch Ministry of Transport is responsible for road construction in the Amsterdam region and explained, "We wanted a low-budget rehabilitation of the motorway section, as a longer stretch of the A6 will undergo reconstruction in about 2-3 years' time. The offer submitted for paving the thin overlay was €500,000 cheaper than for conventional methods of pavement rehabilitation."

The paving team had just two nights to lay new surface course and the three lanes being resurfaced had an overall width of 15m while around the two junctions, the maximum width was 24m. All told, 30,000m2 of asphalt pavement needed rehabilitating. For the right-hand and middle lanes, the paving team used the paver's maximum pave and spray width. And when paving in 6m width, the operating speed of the SUPER 1800-2 with SprayJet Module was a productive 12m/min.

A key advantage of the SprayJet concept system is its ability to apply emulsion and paving asphalt in a single pass, a major benefit when paving thin overlays, hot on hot.

For thin overlays, compaction is a focal issue when it comes to producing a strong and durable bond of layers and this job was handled by a team of three 228 Hamm rollers. Two DV 70 OV tandem rollers compacted the surface, while MNO Vervat used a HW 90 to compact the transition areas. All three rollers operated in static mode and the final density of the 20mm overlay was achieved in just a few passes. The warranty period for the surface is five years although the contractor is convinced this will last considerably longer.

For more information on companies in this article

Related Content

  • Asphalt paving developments
    March 13, 2012
    US and European asphalt paving needs are different, but some firms are bridging that gap, reports Mike Woof. With a clear differentiation between the US and European asphalt paving markets, manufacturers from the latter are now developing machines aimed at the former. The US and European markets for paving machines have developed along very different lines. North American pavers are designed for high throughputs and high paving rates, having been designed to meet a need to build roads over long distances wi
  • Circuit of the Americas Formula for F1 success
    April 4, 2013
    In November 2012, the new Circuit of the Americas (COTA) in Austin, Texas, hosted the first ever Formula 1 US Grand Prix on a purpose-built track. But, as Jeff Winke and Guy Woodford report, the construction of COTA was just as demanding as competing in an F1 race itself For COTA construction contractor Austin Bridge & Road, L.P., nothing was more vital to the successful building of the 5.5km F1 track than meeting the strict criteria for its asphalt-paved surface. “The amount of stress this pavement will un
  • Longer lasting road surfaces with advanced asphalt paving
    February 20, 2012
    Contractors face an array of sophisticated paving technologies, Mike Woof reports. Asphalt paving technology continues to advance as manufacturers develop more efficient and reliable equipment. Paving techniques are also improving, while new polymer modified bitumen materials and recycling methodologies further increase the range of road surfacing options available to the client and contractor.
  • Wirtgen exhibiting diverse machine range at bauma China
    November 12, 2014
    The Wirtgen Group is exhibiting a wide range of its latest machines for the local market at bauma China 2014 in Shanghai. The firm is showing 11 innovations and no fewer than 13 products manufactured locally at the Langfang factory for the Chinese market, from its Road and Mineral Technologies divisions. There are 38 exhibits in total from the Wirtgen Group’s Wirtgen, Vögele, Hamm and Kleemann brands that are tailored to meet Chinese requirements. The Wirtgen brand is exhibiting its powerful WR 250 reclaim