Crack infill system ideal reinstatement solution

Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.
February 17, 2012 Read time: 2 mins
Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.

The problem affecting a large stretch of the M42 close to Birmingham Airport and the nearby NEC Arena in the Midlands region was completed using highways maintenance products from 2314 Stirling Lloyd. It concerned fretted joints in the wheel tract to the road surface.

Faced with the prospect of completely removing the road surface if left untreated, Amey Area 9 (sole provider to the 2309 Highways Agency of management services and maintenance of the motorway network throughout the Midlands) quickly set out to find an effective and durable repair method.

Its search concluded that Stirling Lloyd's HAPAS [Highways Authorities Product Approval Scheme]-approved Safetrack Crack Infill system "was the ideal reinstatement solution." Based on an advanced, fast-curing reactive resin, this high-performance road maintenance system is designed to arrest further decay of the road surface by filling cracks or fretted joints, supporting the edges of the asphalt while preventing water penetration.

Given the stretch of motorway affected and the heavy traffic experienced along this route, Amey Area 9 understandably wanted to test the system on an initial 100m section of the road over a six-week period before committing to the full works. The Safetrack Crack Infill system proved highly successful, both in application and performance, so was selected to complete the remainder of the repair, approximately 17,000m.

To minimise disruption to motorists the works were carried out over a series of night-time closures between 11pm and 4am. Within this five-hour window, specialist contractor, Line Markings, had to set out the traffic management, prepare the crack, apply the Safetrack Crack Infill and remove the traffic control.

Despite the tight time constraint the system's simple but speedy application technique and its fast cure enabled the treatment of approximately 1,000m of motorway per night shift.

Line Markings was able to complete the works in under three weeks, one week ahead of schedule. According to Stirling Lloyd, so impressed was Amey Area 9 with the performance and speed of Safetrack's application that the contractor was asked to return a few weeks later and complete the reinstatement of a further 3,600m of the motorway.

For more information on companies in this article

Related Content

  • Stafford road project underway
    July 8, 2025
    Work is underway in the UK for a key Stafford road project.
  • Caterpillar Paving offers a guide to efficient night time paving practices
    October 3, 2014
    Efficient night-time paving operations can reduce construction costs and cut traffic delays - *Todd Mansell writes As roads become more congested, the user cost of daytime lane closures to accommodate road construction and paving has increased dramatically. One solution to lower user costs associated with traffic delays is to carry out more paving at night during off-peak times. However night-time paving brings new challenges to producing quality work in safely.
  • Flyover removal completed successfully
    February 15, 2021
    A flyover removal project has been completed successfully in the UK.
  • Importance of road/tunnel drainage systems
    April 10, 2012
    A variety of systems are available for quickly and efficiently removing water from roads as Patrick Smith reports The presence of water in a highway layer reduces the bearing capacity of the road, and in doing so it also reduces the structure's lifetime. Indeed, the recent extremely cold winter in many parts of Europe has shown that in colder climates there is a risk of frost damage when water is present resulting in costly potholes, so drainage systems performing properly are important in road design.