Crack infill system ideal reinstatement solution

Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.
February 17, 2012 Read time: 2 mins
Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.

The problem affecting a large stretch of the M42 close to Birmingham Airport and the nearby NEC Arena in the Midlands region was completed using highways maintenance products from 2314 Stirling Lloyd. It concerned fretted joints in the wheel tract to the road surface.

Faced with the prospect of completely removing the road surface if left untreated, Amey Area 9 (sole provider to the 2309 Highways Agency of management services and maintenance of the motorway network throughout the Midlands) quickly set out to find an effective and durable repair method.

Its search concluded that Stirling Lloyd's HAPAS [Highways Authorities Product Approval Scheme]-approved Safetrack Crack Infill system "was the ideal reinstatement solution." Based on an advanced, fast-curing reactive resin, this high-performance road maintenance system is designed to arrest further decay of the road surface by filling cracks or fretted joints, supporting the edges of the asphalt while preventing water penetration.

Given the stretch of motorway affected and the heavy traffic experienced along this route, Amey Area 9 understandably wanted to test the system on an initial 100m section of the road over a six-week period before committing to the full works. The Safetrack Crack Infill system proved highly successful, both in application and performance, so was selected to complete the remainder of the repair, approximately 17,000m.

To minimise disruption to motorists the works were carried out over a series of night-time closures between 11pm and 4am. Within this five-hour window, specialist contractor, Line Markings, had to set out the traffic management, prepare the crack, apply the Safetrack Crack Infill and remove the traffic control.

Despite the tight time constraint the system's simple but speedy application technique and its fast cure enabled the treatment of approximately 1,000m of motorway per night shift.

Line Markings was able to complete the works in under three weeks, one week ahead of schedule. According to Stirling Lloyd, so impressed was Amey Area 9 with the performance and speed of Safetrack's application that the contractor was asked to return a few weeks later and complete the reinstatement of a further 3,600m of the motorway.

For more information on companies in this article

Related Content

  • A vision of roads
    September 3, 2012
    By 2040 European roads could be built differently, and hopefully be safer, according to the EU research programme NR2C
  • Upgrade for Scottish road
    February 17, 2012
    Work is progressing on a £320 million (e385 million) project to upgrade a busy 18km stretch of the main A80 Glasgow-Stirling road in Scotland to motorway standard. The project, between the villages of Stepps and Haggs, is part of a massive infrastructure investment in Scotland's transport network, and construction work includes almost 8km of new dual-lane motorway and hard shoulders between
  • Velocity-Balfour Beatty tackling potholes
    May 13, 2014
    It is the bugbear of motorists worldwide, and costs UK councils alone an estimated US$82.12 million (£50 million) in compensation each year. Now Balfour Beatty is partnering with specialist supplier Velocity and North Somerset Council in south-west England to tackle potholes using innovative technology which vastly reduces disruption to road users. The method, called ‘Spray Injection’ patching, is allowing Balfour Beatty to repair nearly 700 potholes a week on its highways maintenance contract repairing
  • Hydrodemolition equipment helps Swiss bridge rebuild
    December 2, 2014
    A highway bridge in Switzerland has been refurbished with help from hydrodemolition equipment supplied by Aquajet The firm’s latest Rotolance 2500 was used alongside an Aquacutter 710 VE evolution on the Viaduc de Chillon link, above Lake Geneva. The machines were used by Zurich-based hydrodemolition specialist contractor, Walo Hydrodynamik, to remove more than 25,000m³ of concrete deck on the bridge.