Crack infill system ideal reinstatement solution

Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.
February 17, 2012 Read time: 2 mins
Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.

The problem affecting a large stretch of the M42 close to Birmingham Airport and the nearby NEC Arena in the Midlands region was completed using highways maintenance products from 2314 Stirling Lloyd. It concerned fretted joints in the wheel tract to the road surface.

Faced with the prospect of completely removing the road surface if left untreated, Amey Area 9 (sole provider to the 2309 Highways Agency of management services and maintenance of the motorway network throughout the Midlands) quickly set out to find an effective and durable repair method.

Its search concluded that Stirling Lloyd's HAPAS [Highways Authorities Product Approval Scheme]-approved Safetrack Crack Infill system "was the ideal reinstatement solution." Based on an advanced, fast-curing reactive resin, this high-performance road maintenance system is designed to arrest further decay of the road surface by filling cracks or fretted joints, supporting the edges of the asphalt while preventing water penetration.

Given the stretch of motorway affected and the heavy traffic experienced along this route, Amey Area 9 understandably wanted to test the system on an initial 100m section of the road over a six-week period before committing to the full works. The Safetrack Crack Infill system proved highly successful, both in application and performance, so was selected to complete the remainder of the repair, approximately 17,000m.

To minimise disruption to motorists the works were carried out over a series of night-time closures between 11pm and 4am. Within this five-hour window, specialist contractor, Line Markings, had to set out the traffic management, prepare the crack, apply the Safetrack Crack Infill and remove the traffic control.

Despite the tight time constraint the system's simple but speedy application technique and its fast cure enabled the treatment of approximately 1,000m of motorway per night shift.

Line Markings was able to complete the works in under three weeks, one week ahead of schedule. According to Stirling Lloyd, so impressed was Amey Area 9 with the performance and speed of Safetrack's application that the contractor was asked to return a few weeks later and complete the reinstatement of a further 3,600m of the motorway.

For more information on companies in this article

Related Content

  • Diamond in the Pearl: China’s Hong Kong-Zhuhai-Macao Bridge complex
    March 8, 2018
    People in the Pearl River Delta are celebrating the Chinese New Year with the imminent opening of the Hong Kong-Zhuhai-Macao Bridge. David Arminas reviews progress. China’s Spring Festival, or Lunar New Year, is celebrated with the usual enthusiasm and spectacular fireworks. But celebrations will be particularly joyous for many people in the southern Pearl River Delta. The soon-to-be-open Hong Kong-Zhuhai-Macao Bridge (HZMB) will slash travel time between the Hong Kong Special Administrative Region, Zhuh
  • Epic demolition work for Epiroc in Germany
    November 30, 2023
    A demolition firm in Germany has made good use of hydraulic breakers from Epiroc.
  • Completion due shortly for UK’s A30 project
    February 11, 2025
    Completion of the UK’s A30 upgrade project is due shortly.
  • Cat paves the way in Portugal
    June 22, 2012
    Caterpillar pavers were used recently to help improve drainage on a vital road into a popular tourist destination in Portugal. The Avenida Marginal is the main road access into Cascais, a village with historic hotels, winding roads and stunning views of the Atlantic Ocean attracting thousands of holidaymakers each year. However, the highway had been suffering from poor draining resulting in rivulets being formed in heavy rain, making travelling hazardous for cars and pedestrians alike.