Crack infill system ideal reinstatement solution

Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.
February 17, 2012 Read time: 2 mins
Overnight repair work on a major English motorway has avoided the major traffic disruption and significantly increased road surfacing costs that would have occurred if left untreated.

The problem affecting a large stretch of the M42 close to Birmingham Airport and the nearby NEC Arena in the Midlands region was completed using highways maintenance products from 2314 Stirling Lloyd. It concerned fretted joints in the wheel tract to the road surface.

Faced with the prospect of completely removing the road surface if left untreated, Amey Area 9 (sole provider to the 2309 Highways Agency of management services and maintenance of the motorway network throughout the Midlands) quickly set out to find an effective and durable repair method.

Its search concluded that Stirling Lloyd's HAPAS [Highways Authorities Product Approval Scheme]-approved Safetrack Crack Infill system "was the ideal reinstatement solution." Based on an advanced, fast-curing reactive resin, this high-performance road maintenance system is designed to arrest further decay of the road surface by filling cracks or fretted joints, supporting the edges of the asphalt while preventing water penetration.

Given the stretch of motorway affected and the heavy traffic experienced along this route, Amey Area 9 understandably wanted to test the system on an initial 100m section of the road over a six-week period before committing to the full works. The Safetrack Crack Infill system proved highly successful, both in application and performance, so was selected to complete the remainder of the repair, approximately 17,000m.

To minimise disruption to motorists the works were carried out over a series of night-time closures between 11pm and 4am. Within this five-hour window, specialist contractor, Line Markings, had to set out the traffic management, prepare the crack, apply the Safetrack Crack Infill and remove the traffic control.

Despite the tight time constraint the system's simple but speedy application technique and its fast cure enabled the treatment of approximately 1,000m of motorway per night shift.

Line Markings was able to complete the works in under three weeks, one week ahead of schedule. According to Stirling Lloyd, so impressed was Amey Area 9 with the performance and speed of Safetrack's application that the contractor was asked to return a few weeks later and complete the reinstatement of a further 3,600m of the motorway.

For more information on companies in this article

Related Content

  • Key Qatar tunnel waterproofing project
    May 17, 2017
    Technology from Stirling Lloyd is being used to waterproof the recently constructed Lusail Tunnel in Qatar. The construction of the tunnel is a major project as it forms part of a new US$30 billion integrated transportation system in Qatar. The new Lusail CP07-C-1-A Commercial Boulevard, Road A3 Troughs, Underpass and Tunnel project is designed to provide a connection from the recently established Lusail City to the heart of Doha in Qatar. The cut and cover tunnel provides fast access to the new Lusail City
  • Installation underway of first UK M4/M5 ‘superspan’ gantries
    July 4, 2012
    The installation is underway of the first superspan gantries on the M4/M5 managed motorway scheme. The existing gantries and infrastructure were successfully removed last month while the new steel gantries were being constructed, fitted-out and tested at a dedicated facility located near junction 17 of the M5, before being delivered to the works site. A total of 33 new overhead gantries, a number of which span 50m and weigh over 30tonnes, will be installed along the new managed motorway section up until T
  • Cold recycling helps rebuild of Brazil’s Ayrton Senna highway
    September 28, 2015
    Brazil’s Ayrton Senna Highway has been rebuilt using cold recycling. Brazil’s SP-070 is also known as the Ayrton Senna Highway and is a major highway in the country, carrying heavy traffic volumes. For its rebuild, the time-saving, cost-efficient and eco-friendly benefits of the cold recycling process have been put to the test. The SP-070 provides a key transport link between São Paulo and Campos do Jordão, Vale do Paraíba and Rio de Janeiro, as well as being the main access route to Guarulhos Interna
  • Reduced emissions, costs, with recycled asphalt
    February 21, 2012
    Recycling is a key issue for asphalt road construction, with many technologies now coming to market. Bith an ever increasing emphasis on sustainability forcing change in the construction sector in Europe and North America, the highway sector now has to seek new solutions.