Airbase refurbishment with Volvo CE pavers

Asphalt pavers from Volvo CE have played an important role in the renovation of an airport runway at the Wunstorf air base in Germany. The contractor Strabag faced the challenge of placing new asphalt on the runway in the shortest possible time.
May 13, 2022 Read time: 2 mins
Volvo CE pavers working in echelon were able to pave a military airbase runway in a single day

The firm used three pavers working in echelon for the large-scale project, which presented challenges in terms of both planning and precision. The firm used modern Volvo P7820D ABG pavers and also benefited from support of paving experts from Volvo CE.

The Wunstorf air base handles large transport aircraft in the shape of Airbus A400Ms as the Air Transport Wing 62 of the German armed forces (Bundeswehr) stationed at the military airfield, which is located north-west of Hanover.

Jörg Hebemeyer, road construction manager at Strabag's Hanover division explained that the firm had been rehabilitating the second runway in Wunstorf for over a year before the pavers could be used. Trucks carrying fresh asphalt had to drive up almost every minute once paving commenced so as to supply the three asphalt trains, each consisting of a road paver and a feeder. To complete the work, the teams were followed by rollers to finish the paving job.

With this setup, the firm was able to finish asphalting the entire runway within three days.

For Hebemeyer, who has been working at Strabag since 2018, it was a challenging project that demanded a lot from everyone involved. "In the end, we never had any problems with this project at any time.”

Michael Weinhold, one of the responsible paving foremen on site, commented that using the three pavers in echelon meant a paving width of 30m could be achieved.

Frank Dörrie, product manager Road Pavers at Volvo CE, and André Sebastian Meier, product manager Road Pavers & Rollers Germany, Austria, Switzerland, travelled to the site for the job. “You don't experience a project like this every day," said Dörrie.

Although the area was large, using three of the Volvo P6820D ABG pavers allowed Strabag to asphalt the entire runway in just one day.

For more information on companies in this article

Related Content

  • Asphalt paving review for 2019
    February 12, 2020
    A series of new asphalt pavers have been introduced in 2019
  • Tunnelling challenge on German project
    June 13, 2012
    A massive construction project has been underway deep in the heart of the Schnecktal valley area in Germany. From the surface, though, you would never be able to tell. The majority of the work is underground, as a joint-venture team led by German contractor Wayss and Freytag Ingenieurbau builds the nearly 7km long Finne Tunnel. After a few years of tunnel boring operations, the contractor is at work finishing the interior of the tunnel, slipforming first the tunnel’s floor and then a walkway with its GOMACO
  • High quality Swedish stone
    February 10, 2012
    Close to Sweden's second largest city Göthenburg lies the efficient Jehander quarrying operation run by Heidelberg Cement. The site produces around 9,000tonnes/day at peak seasonal demand and has an output of some 1,000,000tonnes/year. The site has recently renewed its operating permission and now has the necessary approval to work until 2021.
  • Micro surfacing the Brooklyn Bridge with Bergkamps’ M210 paver
    May 16, 2018
    A major job for micro surfacing took place on the Brooklyn Bridge near New York. It was the third time in Ken Messina’s career that he would provide micro surfacing for the iconic Brooklyn Bridge, built in 1883. Messina, as president of New Jersey-based Asphalt Paving Systems (APS), knew only too well the challenges that lay ahead. And there were many. There would be only a brief window of opportunity for paving, with lane closures starting at 10pm and ending at 5am. The cool, humid atmosphere would a