Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Swell times for swale construction with a Sidewinder
    October 9, 2018
    Specialised swale construction featured in Northern England recently UK contractor Balfour Beatty examined different methods for building swales along the Norwich Northern Distributor Road near the English city of Norwich. Balfour decided to trial specialised road-widening machines, specially configured excavator buckets and modified compaction equipment. Excavators and dump trucks prepared the area for placement of sub-base material. The swale areas were constructed using both conventional methods as wel
  • Colas eases congestion with new Thornbury Barracks roundabout
    April 27, 2015
    In the UK, Colas is near completion of the Thornbury Barracks roundabout aimed to reduce traffic congestion on the A647 highway, the principal link between Leeds and Bradford in the county of West Yorkshire. Traffic signals have been placed on the junction, with central running lanes constructed through the previous roundabout. Michael Holmes, Colas business manager for the Leeds area, explained there was a need to infill a local pedestrian subway underpass using foam concrete, and option not previously u
  • Spray paving with Vӧgele and Dynapac
    March 8, 2023
    Applying emulsion and carrying out asphalt paving in a single operation can boost efficiency and save much money.
  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v