Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s
  • UAE quarry facility boosting productivity
    May 15, 2015
    A United Arab Emirates quarry is putting its Volvo fleet to the test in harsh conditions A quarrying facility in the United Arab Emirates (UAE), is boosting output following the commissioning of a new machine fleet for loading and hauling duties. The quarry is located in the northeast of the UAE in Fujairah, an emirate almost entirely surrounded by mountains. This rugged landscape is the product of an estimated 800 million years of geological activity and is the source of a high quality limestone used in
  • Deep and wide with Wirtgen’s W 100 CFi compact milling machine
    May 14, 2018
    The spread of fibre-optic cables, especially for broadband internet access, is advancing rapidly across the world. The Upper Austrian district of Schärding, not far from the German border, is no exception. Engelhartszell is the second community to benefit from this technology. And the contractor, Hemmelmair Frästechnik from Linz, is also making use of cutting-edge technology - in this case made from steel and carbide. A Wirtgen W 100 CFi compact milling machine with deep milling unit is being used for tren
  • Importance of road/tunnel drainage systems
    April 10, 2012
    A variety of systems are available for quickly and efficiently removing water from roads as Patrick Smith reports The presence of water in a highway layer reduces the bearing capacity of the road, and in doing so it also reduces the structure's lifetime. Indeed, the recent extremely cold winter in many parts of Europe has shown that in colder climates there is a risk of frost damage when water is present resulting in costly potholes, so drainage systems performing properly are important in road design.