Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • GPS machine control speeds dangerous road improvement
    April 11, 2012
    A Canadian contractor has carried out major roadworks to improve safety on a dangerous stretch of road, using technology to complete the work smoothly. Wiltech Developments, located in West Kelowna, British Columbia, has a great deal of experience. In the contracting sector. The firm works in most. of British Columbia and currently owns more than 40 pieces of heavy machinery, with the majority of these units featuring Trimble Grade Control equipment, a move that has improved its operations.
  • Versatile pavement re-texturing machine
    February 6, 2012
    AN INNOVATIVE wet steel shotblasting machine developed by pavement re-texturing specialist Klaruw is now being tested in the UK.
  • Elevated thinking
    July 30, 2019
    A Swiss-designed system for the diversion of traffic away from road maintenance crews could be revolutionary, reports David Arminas Switzerland will soon tender for companies to build and supply a mobile system for physically shifting traffic away from bridge and road maintenance crews. The federal highways agency - FEDRO - will be asking manufacturers of heavy equipment to submit bids starting this summer for the Astra Bridge system. The system will be two lanes wide and include ramp sections at e
  • Eurovia races against the clock for London’s Race of Champions
    June 17, 2016
    Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium. The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award. The circuit was co