Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Warm mix asphalt offers green solution
    September 4, 2019
    A new report from the UK highlights that utilising warm mix asphalt (WMA) can help cut CO2 emissions. The All-Party Parliamentary Group on Highways has issued a report highlighting how the use of WMA can reduce carbon emissions and improve efficiencies on highways projects. WMAs are manufactured and laid at lower temperatures than traditional asphalts, using less energy and delivering carbon savings without compromising performance. Their use can reduce CO2 emissions associated with asphalt production for
  • Highways England to upgrade Winchester M3 junction
    July 5, 2019
    Highways England has unveiled plans to upgrade to one of the busiest motorway junctions in southern England near the town Winchester. Under the plans, junction 9 - the Winchester junction where the M3 interchanges with the A34 trunk road - will be redesigned to create dedicated free flow lanes. This goal is to allow drivers travelling between the M3 and the A34 to travel freely between the two roads to avoid using the junction roundabout. The M3 is the main road between London and the Solent Ports or
  • Simple road safety measures save lives
    February 15, 2012
    Elementary road safety measures quickly pay back the costs of investment and, more importantly, help save lives as Patrick Smith reports. More than 300 people in the UK are alive today or have avoided the prospect of a lifetime of special care because just 15 roads have had simple improvements put in place.
  • Innovative machine control systems for Canadian slipforming work
    November 29, 2013
    Advanced machine control technologies are speeding site layout and construction operations Canadian house building firm Mattamy Homes has brought in a contractor that has used sophisticated equipment to build the roads around its new development in Oakville, Ontario. The site is just 30 minutes drive from Toronto. Phase 1-A of the project is under construction and nearly every one of the 550 homes that will be built there has been sold already. Additional phases will bring the total number of homes to 1,800