Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Marini mobility option
    June 4, 2019
    Marini is offering new versions of its Xpress plant. The first version was the Xpress 2500, but the range is now being widened with the addition of the Xpress 1500, 1500P, 2000 and 2000P models. Andrea Zanoletti is in charge of this range and explained that the plants are designed for maximum mobility. He said, “With only two trailers, you have a complete asphalt plant.” The existing Xpress 2500 model offers an output of up to 250tonnes/hour. However, the new Xpress 1500 and 1500P offer outputs of 150
  • £317 million UK highway project delayed
    February 12, 2025
    A £317 million UK highway project is delayed.
  • £8 billion UK tunnel project to go ahead
    January 30, 2025
    The £8 billion UK Lower Thames Crossing tunnel project is to go ahead.
  • Developments in noise-reducing road surfaces
    February 17, 2012
    Mixtures with special additives are being produced for roads, offering noise reduction and aiding recycling. Patrick Smith reports. Noise-reducing road surfacings have been used in motorway construction for some time. But relatively new are noise-optimised surfacings used on roads in towns that do not follow a standard concept.Road trials with these materials have taken place in Germany since 2007 and have been prioritised due to the European Union Guidelines on the Assessment and Management of Environmenta